7 unique locations - 3.5MW total capacity

SIMEC Lochaber Power Lochaber Smelter North Road Fort William PH336TH (65 components)
• Hydro power turbine generator Unit 1 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
• Hydro power turbine generator Unit 3 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
• Hydro power turbine generator Unit 4 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
443.26 MW
School Road, Aberdeen AB24 1TU (19 components)
• BM Unit T_FFES-3 at Ffestiniog Power Station (Pumped Storage)
• District heating implementation with one asset 1.943MW exporting excess to distribution network. Primary fuel type = Natural Gas. All generation unit capacities are nominal and allow for site-specific variations.
• bus depot site
Active • 2028-29 (T-4), 2027-28 (T-4) ...
3.48 MW
Montgomery Road, Aberdeen AB24 2YA (17 components)
• District heating implementation with one asset 0.996MW exporting excess to distribution network, Primary fuel type = Natural Gas
• District heating implementation with one asset 0.996MW exporting excess to distribution network, Primary fuel type = Natural Gas. All generation unit capacities are nominal and allow for site-specific variations.
• bus depot site
Active • 2028-29 (T-4), 2025-26 (T-4) ...
4.32 MW
Heathfield Landfill, John Acres Lane, Kingsteignton, Devon, TQ12 3GP (3 components)
• DSR Component providing load turn down at a data centre
• OCGT from Grain U4. Fuel is Gas Oil as specified in BS 2869 Class A2
• The CMU at the Heathfield Landfill site in Devon will be made up of three reciprocating engines generating from natural gas. In their current state, these engines have been designed to generate from landfill gas, but will be converted to natural gas and then recommissioned, ahead of the delivery year. The three components of the CMU (referenced VIR074, VIR079 and VIR080) are Cummins QSV91 units, built in 2008 and rated at 1,750kW. Each engine generates at 415V, which is then stepped up to 11kV and then to 33kV for export.
Inactive • 2023-24 (T-4), 2022-23 (T-3) ...
EDF Energy (Thermal Generation) Limited, Cottam Power Station, Outgang Lane, Cottam, Retford, DN22 0NP (46 components)
• 2MW - 2.3MWh Battery Energy Storage System
• CMU INO200 represents demand assets on the Inovyn ChlorVinyls Ltd site in Runcorn, Cheshire. The asset uses electricity for Chemical manufacture. Site load can easily be altered to suit demand or reduction.
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms. Placeholder component for empty Unproven DSR CMU - Load Reduction upon instruction
Active • 2027-28 (T-4), 2025-26 (T-4) ...
1528.52 MW
EDF Energy, Hinkley Point B power station, Nr Bridgwater, Somerset, TA5 1UD (56 components)
• Hinkley Point B Power Station CMU 7: [HP7-22] T_HINB-7 + (50% x T_HINB-D)
• Hinkley Point B Power Station CMU 7: [HP7-23] T_HINB-7 + (50% x T_HINB-D)
• Hinkley Point B Power Station CMU 8: [HP8-23] T_HINB-8 + (50% x T_HINB-D)
Active • 2027-28 (T-4), 2026-27 (T-4) ...
1771.09 MW
Ashgrove Road West, Aberdeen AB16 5UL (17 components)
• District heating implementation with one asset 1.013MW exporting excess capacity to distribution network. Primary fuel type = Natural Gas.
• District heating implementation with one asset 1.013MW exporting excess capacity to distribution network. Primary fuel type = Natural Gas. All generation unit capacities are nominal and allow for site-specific variations.
• bus depot site
Active • 2028-29 (T-4), 2027-28 (T-4) ...
1.81 MW
Loading map...