CENTRICA BUSINESS SOLUTIONS UK OPTIMISATION LIMITED

69 unique locations (1216 components) - Page 1 of 3

Active MW: 1658.75 MW
Inactive MW: 3375.49 MW
Westexe, Tiverton, Devon, EX16 5LL (11 components)

2026 kW CHP unit

Active • 2026-27 (T-4), 2025-26 (T-4) ...
Stanlow Manufacturing Complex, Ellesmere Port, Cheshire, CH65 4HB (9 components)
• 2 x On-site turbo alternators
• 6 x On-site turbo alternators
• Power Recovery Train
Active • 2019-20 (T-1)
Saddlebow Industrial Estate, Poplar Avenue, King's Lynn PE34 3AL. (23 components)
• Power Station for Paper plant made up of 1x35MW Gas engine
• Power Station for Paper plant made up of 1x35MW Gas engine plus 1x12MW steam turbine
Active • 2026-27 (T-4), 2025-26 (T-4) ...
Priory Street, Ware, Hertfordshire, SG12 0DJ (22 components)

On-site existing CHP generating unit

Active • 2024-25 (T-4), 2023-24 (T-4) ...
Poplar Avenue, King' Lynn, PE34 3AL (16 components)

Palm Paper Limited operates a large paper making site in King's Lynn, Norfolk. The onsite industrial process is an energy intensive paper recycling and manufacturing plant. Palm Paper plans to …

Active • 2026-27 (T-4), 2025-26 (T-4) ...
17.99 MW
Park Road, Ware. Hertfordshire, SG12 0DP (42 components)

On-site existing CHP generating unit

Active • 2024-25 (T-4), 2023-24 (T-4) ...
North Lonsdale Road, Cumbria, Ulverston, LA12 9DR (29 components)

On-site existing CHP generating unit

Active • 2022-23 (T-3), 2022-23 (T-4) ...
North Avenue, Marston Green, Birmingham, B40 1NT. (12 components)

Gas Generator - ENER-G 1521 - proposed to be installed on land to the north-east elevation of Hall 5 at the NEC Site.

Active • 2024-25 (T-4), 2023-24 (T-4) ...
North Avenue, Marston Green, Birmingham, B40 1NT (26 components)
• CHP Unit 850kWe proposed to be installed in Hall 6-8 at NEC site
• Gas Generation units at 1013kWe
• Proposed CHP Unit 850kWe to be installed in Hall 6-8 at NEC site
Active • 2024-25 (T-4), 2023-24 (T-4) ...
2.92 MW
National Distribution Centre, Barnsdale Way, Grove Park, Leicester, Leicestershire, LE19 1SU. (1 component)

Distribution Centre with behind the meter back up generation

Active • 2024-25 (T-4)
National Distribution Centre, Barnsdale Way, Grove Park, Leicester, LE19 1SU (12 components)

Distribution Centre with behind the meter back-up generation.

Active • 2023-24 (T-4), 2022-23 (T-3) ...
Moorcroft Drive Wednesbury WS10 7DE (13 components)

EnerG 1000 CHP

Active • 2026-27 (T-4), 2025-26 (T-4) ...
Melton Ross Quarries Barnetby, North Lincolnshire, DN38 6AE (6 components)
• 0.8 MWe Gas Powered Generation Unit
• 0.8 MWe Gas powered generator
Active • 2019-20 (T-1), 2018-19 (T-1)
Maidenhead Road, Windsor, SL4 5GD (15 components)
• Battery Storage
• Battery storage
• Battery strorage unit
Active • 2024-25 (T-4), 2023-24 (T-4) ...
Knapton Generating Station, East Knapton, Malton, North Yorkshire, YO17 8JF (8 components)

Generating Station, the power generation facilities consist of RLM 6000 EGT generation package with a LM6000 gas turbine

Active • 2019-20 (T-1), 2018-19 (T-1)
Loading map...