Braehead Farm Riccarton Kilmarnock KA1 5LN
KA1 5LN
Last updated: 29 Jul 2025 21:51 UTC
4 Components Storage (Duration 2h) KILMARNOCK ENERGY CENTRE LIMITED
Total Capacity: 71.20 MW
Components: 4
Technologies:
Storage (Duration 2h)
Unique CMUs: 1

Secondary Trading Contacts

Contact Information

Component Descriptions

A new battery storage system comprising batteries, containers, inverters, control systems and associated balance of plant. This will be constructed on agricultural land, approximately 250 Metres north of Kilmarnock Substation. Metering of output is Net of auxiliary load.

Used by 1 CMU

CMU Identifiers

1 CMU at this location (showing first 1):

KECL24

Components at this Location

Click on yellow auction year badges to see individual component pages

A new battery storage system comprising batteries, containers, inverters, control systems and associated balance of plant. This will be constructed on agricultural land, approximately 250 Metres north of Kilmarnock Substation. Metering of output is Net of auxiliary load.
CMU: KECL24
Storage (Duration 2h) KILMARNOCK ENERGY CENTRE LIMITED Parent: Green Bess Developments (Uk) Limited
Capacity Information:
De-Rated Capacity (Registry) 71.196
Connection/DSR Capacity 340
Anticipated Capacity 71.196