Land north of Coxmoor Wood, off Crondall Road, Crookham Village, Fleet, GU51 5SU - A 47.500 MW / 71.250 MWh battery energy storage system

Component ID: FLEE02
Last updated: 27 Jul 2025 10:50 UTC
CMU ID:
Primary Fuel:
Storage - Battery
Description:
A 47.500 MW / 71.250 MWh battery energy storage system
Auction:
2028-29 (T-4) Four Year Ahead Capacity Auction

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) 7.49 MW
  • De-Rated Capacity (CMU Registry) 7.49
  • Connection Capacity (CMU Registry) 47.50 MW
  • Anticipated Capacity (CMU Registry) 7.49 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name FLEET GREEN LIMITED
  • Parent Company (CMU Registry) Cero Generation Holdings UK Limited
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +447539073251

Field Value
_id 534872
Type T-4
rank 0.0706241
CMU ID FLEE02
Auction Name 2028-29 (T-4) Four Year Ahead Capacity Auction
Component ID FLEE02
Delivery Year 2028
De-Rated Capacity 7.491
OS Grid Reference SU 784 515
Location and Post Code Land north of Coxmoor Wood, off Crondall Road, Crookham Village, Fleet, GU51 5SU
Connection / DSR Capacity 47.5
Primary Fuel of Component Storage - Battery
Generating Technology Class Storage (Duration 1.5h)
Description of CMU Components A 47.500 MW / 71.250 MWh battery energy storage system
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 15535
Type T-4
CMU ID FLEE02
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2028-29 (T-4) Four Year Ahead Capacity Auction
CM Unit Name FLEET BESS
CM Unit Type CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2028
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company Cero Generation Holdings UK Limited
DSR Test Method (empty)
Is FCM required Yes
CM Unit Category New Build Generating CMU
Storage Facility Yes
De-Rated Capacity 7.491
Name of Applicant FLEET GREEN LIMITED
Primary Fuel Type Storage - Battery
Registered Holder FLEET GREEN LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover 74910
Termination Fee 1 Rate Β£5000.00 /MW
Termination Fee 2 Rate Β£25000.00 /MW
Termination Fee 3 Rate Β£10000.00 /MW
Termination Fee 4 Rate Β£15000.00 /MW
Termination Fee 5 Rate Β£35000.00 /MW
Connection / DSR Capacity 47.5
Maximum Obligation Period 15
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Transmission
Unique Agreement Identifier CAN-2028-FLEE02-001
New Build Yet to Satisfy FCM Yes
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 7.491
Term of the Capacity Agreement 15
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2025-04-04
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 7.491
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+447539073251
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 15
Date for Financial Commitment Milestone 2026-07-21
Delivery Years for which Agreement Valid 2028/2029, 2029/2030, 2030/2031, 2031/2032, 2032/2033, 2033/2034, 2034/2035, 2035/2036, 2036/2037, 2037/2038, 2038/2039, 2039/2040, 2040/2041, 2041/2042, 2042/2043
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved 2027-07-01
Subject to Substantial Completion Milestone Yes
Subject to a Minimum Completion Requirement Yes
Earliest Date SCM is expected to be achieved 2027-01-13
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 15
Long-Stop Date for the Minimum Completion Requirement 2029-10-01