St Marks Boilerhouse Donaldson Road LEICESTER Leicestershire LE4 6BF - Combined Heat and Power Plant, St Marks Boiler House, capacity of generator 1.600MW. Although the supplier of the settled hh meter has provided their three peaks, we have used the combined peak of all the component units to determine the capacity of LDEC as a single CMU hence the connected capacity above being consistent with the three peaks of the combined units.

Component ID: CES208
Last updated: 27 Jul 2025 13:16 UTC
CMU ID:
Description:
Combined Heat and Power Plant, St Marks Boiler House, capacity of generator 1.600MW. Although the supplier of the settled hh meter has provided their three peaks, we have used the combined peak of all the component units to determine the capacity of LDEC as a single CMU hence the connected capacity above being consistent with the three peaks of the combined units.
Auction:
2025-26 (T-4) Four Year Ahead Capacity Auction

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 4.20
  • Connection Capacity (CMU Registry) 4.58 MW
  • Anticipated Capacity (CMU Registry) 4.20 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name LEICESTER DISTRICT ENERGY COMPANY LIMITED
  • Parent Company (CMU Registry) BRING ENERGY GROUP LIMITED
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4407811071199

Field Value
_id 268691
Type T-4
rank 0.0573088
CMU ID CES208
Auction Name 2025-26 (T-4) Four Year Ahead Capacity Auction
Component ID NOR001
Delivery Year 2025
De-Rated Capacity (empty)
OS Grid Reference SK 593 057
Location and Post Code St Marks Boilerhouse Donaldson Road LEICESTER Leicestershire LE4 6BF
Connection / DSR Capacity (empty)
Primary Fuel of Component (empty)
Generating Technology Class Combined Heat and Power (CHP)
Description of CMU Components Combined Heat and Power Plant, St Marks Boiler House, capacity of generator 1.600MW. Although the supplier of the settled hh meter has provided their three peaks, we have used the combined peak of all the component units to determine the capacity of LDEC as a single CMU hence the connected capacity above being consistent with the three peaks of the combined units.
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 14367
Type T-4
CMU ID CES208
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2027-28 (T-4) Four Year Ahead Capacity Auction
CM Unit Name LDEC
CM Unit Type Non CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2027
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company BRING ENERGY GROUP LIMITED
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category Existing Generating CMU
Storage Facility No
De-Rated Capacity 4.196
Name of Applicant LEICESTER DISTRICT ENERGY COMPANY LIMITED
Primary Fuel Type Gas
Registered Holder LEICESTER DISTRICT ENERGY COMPANY LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate Β£5000.00 /MW
Termination Fee 2 Rate Β£25000.00 /MW
Termination Fee 3 Rate Β£10000.00 /MW
Termination Fee 4 Rate Β£15000.00 /MW
Termination Fee 5 Rate Β£35000.00 /MW
Connection / DSR Capacity 4.581
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2027-CES208-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 4.196
Term of the Capacity Agreement 1
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2024-04-08
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 4.196
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+4407811071199
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2027/2028
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 1
Long-Stop Date for the Minimum Completion Requirement (empty)