Home Technologies Companies Locations Map Explorer FAQ Trading Board Buy Me A Coffee Help Login Register
Theme
Light Dark Auto

LAND ADJACENT TO WORMALD GREEN SUB-STATION, STATION LANE, WORMALD GREEN, HARROGATE, HG3 3RX - New Build 33 MW Battery Energy Storage system

Component ID: HWGL22
Last updated: 30 Jul 2025 19:30 UTC
CMU ID:
Description:
New Build 33 MW Battery Energy Storage system
Auction:
2026-27 (T-4) Four Year Ahead Capacity Auction

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) 5.86 MW
  • De-Rated Capacity (CMU Registry) 5.86
  • Connection Capacity (CMU Registry) 33 MW
  • Anticipated Capacity (CMU Registry) 5.86 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name HEIT WG LIMITED
  • Parent Company (CMU Registry) HEIT Holdings Ltd
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) 02080921890

Field Value
_id 194080
Type T-4
rank 0.0706241
CMU ID HWGL22
Auction Name 2026-27 (T-4) Four Year Ahead Capacity Auction
Component ID HWGL22
Delivery Year 2026
De-Rated Capacity 5.864
OS Grid Reference SE 313 645
Location and Post Code LAND ADJACENT TO WORMALD GREEN SUB-STATION, STATION LANE, WORMALD GREEN, HARROGATE, HG3 3RX
Connection / DSR Capacity 33
Primary Fuel of Component (empty)
Generating Technology Class Storage (Duration 1.5h)
Description of CMU Components New Build 33 MW Battery Energy Storage system
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 13825
Type T-4
CMU ID HWGL22
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2026-27 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Wormald Green ESS
CM Unit Type CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2026
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company HEIT Holdings Ltd
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category New Build Generating CMU
Storage Facility Yes
De-Rated Capacity 5.864
Name of Applicant HEIT WG LIMITED
Primary Fuel Type Storage - Battery
Registered Holder HEIT WG LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate Β£5000.00 /MW
Termination Fee 2 Rate Β£25000.00 /MW
Termination Fee 3 Rate Β£10000.00 /MW
Termination Fee 4 Rate Β£15000.00 /MW
Termination Fee 5 Rate Β£35000.00 /MW
Connection / DSR Capacity 33
Maximum Obligation Period 15
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2026-HWGL22-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 5.864
Term of the Capacity Agreement 15
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2023-03-31
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 5.864
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone 02080921890
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 15
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2026/2027, 2027/2028, 2028/2029, 2029/2030, 2030/2031, 2031/2032, 2032/2033, 2033/2034, 2034/2035, 2035/2036, 2036/2037, 2037/2038, 2038/2039, 2039/2040, 2040/2041
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved 2024-07-30
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved 2024-03-30
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 15
Long-Stop Date for the Minimum Completion Requirement (empty)