Home Technologies Companies Locations Map Explorer FAQ Trading Board Buy Me A Coffee Help Login Register
Theme
Light Dark Auto

Land south of Walpole Substation, Walpole Bank, Norfolk, PE14 7JE. - Lithium-based battery energy storage system.

Component ID: WALPO1
Last updated: 01 Aug 2025 08:30 UTC
CMU ID:
Primary Fuel:
Storage - Battery
Description:
Lithium-based battery energy storage system.
Auction:
2024-25 (T-1) One Year Ahead Capacity Auction

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 11.34
  • Connection Capacity (CMU Registry) 50 MW
  • Anticipated Capacity (CMU Registry) 11.34 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name WALPOLE GREEN LIMITED
  • Parent Company (CMU Registry) VERDANT BIDCO LIMITED
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4407572874292

Field Value
_id 277532
Type T-1
rank 0.0573088
CMU ID WALPO1
Auction Name 2024-25 (T-1) One Year Ahead Capacity Auction
Component ID WALPOL
Delivery Year 2024
De-Rated Capacity 11.335
OS Grid Reference TF 483 165
Location and Post Code Land south of Walpole Substation, Walpole Bank, Norfolk, PE14 7JE.
Connection / DSR Capacity 50
Primary Fuel of Component Storage - Battery
Generating Technology Class Storage (Duration 2h)
Description of CMU Components Lithium-based battery energy storage system.
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 10877
Type T-1
CMU ID WALPO1
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2024-25 (T-1) One Year Ahead Capacity Auction
CM Unit Name Walpole
CM Unit Type CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2024
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company VERDANT BIDCO LIMITED
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category New Build Generating CMU
Storage Facility Yes
De-Rated Capacity 11.335
Name of Applicant WALPOLE GREEN LIMITED
Primary Fuel Type Storage - Battery
Registered Holder (empty)
Annual Penalty Cap (empty)
Monthly Penalty Cap (empty)
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate (empty)
Termination Fee 2 Rate (empty)
Termination Fee 3 Rate (empty)
Termination Fee 4 Rate (empty)
Termination Fee 5 Rate (empty)
Connection / DSR Capacity 50
Maximum Obligation Period 1
Capacity Agreement Awarded (empty)
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Transmission
Unique Agreement Identifier (empty)
New Build Yet to Satisfy FCM Yes
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 11.335
Term of the Capacity Agreement (empty)
Nature of the Security Interest (empty)
CMU confirmed entry into Auction No
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement (empty)
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation (empty)
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+4407572874292
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded (empty)
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid (empty)
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round (empty)
Long-Stop Date for the Minimum Completion Requirement (empty)