Home Technologies Companies Locations Map Explorer FAQ Trading Board Buy Me A Coffee Help Login Register
Theme
Light Dark Auto

Llay Grid Capacity Site Llay Hall Farm Llay Wrexham LL12 0TH - 3MW of installed capacity of gas fuelled reciprocating engines to be installed on designated land.

Component ID: LLAY19
Last updated: 22 Jul 2025 07:43 UTC
CMU ID:
Description:
3MW of installed capacity of gas fuelled reciprocating engines to be installed on designated land.
Auction:
2023-24 (T-4) Four Year Ahead Capacity Auction

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 2.85
  • Connection Capacity (CMU Registry) 3 MW
  • Anticipated Capacity (CMU Registry) 2.85 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name BIOGAS TECHNOLOGY LIMITED
  • Parent Company (CMU Registry) Ylem Group Limited
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4401616602222

Field Value
_id 277626
Type T-4
rank 0.0706241
CMU ID LLAY19
Auction Name 2023-24 (T-4) Four Year Ahead Capacity Auction
Component ID LLAY19
Delivery Year 2023
De-Rated Capacity (empty)
OS Grid Reference SJ 319 562
Location and Post Code Llay Grid Capacity Site Llay Hall Farm Llay Wrexham LL12 0TH
Connection / DSR Capacity (empty)
Primary Fuel of Component (empty)
Generating Technology Class Reciprocating engines
Description of CMU Components 3MW of installed capacity of gas fuelled reciprocating engines to be installed on designated land.
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 10015
Type T-4
CMU ID LLAY19
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2023-24 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Llay
CM Unit Type Non CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2023
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company Ylem Group Limited
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category New Build Generating CMU
Storage Facility No
De-Rated Capacity 2.849
Name of Applicant BIOGAS TECHNOLOGY LIMITED
Primary Fuel Type Gas
Registered Holder (empty)
Annual Penalty Cap (empty)
Monthly Penalty Cap (empty)
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate (empty)
Termination Fee 2 Rate (empty)
Termination Fee 3 Rate (empty)
Termination Fee 4 Rate (empty)
Termination Fee 5 Rate (empty)
Connection / DSR Capacity 3
Maximum Obligation Period 15
Capacity Agreement Awarded No
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier (empty)
New Build Yet to Satisfy FCM Yes
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 2.849
Term of the Capacity Agreement (empty)
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement (empty)
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation (empty)
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+4401616602222
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded (empty)
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid (empty)
Connection Agreement Deferral Declaration Yes
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 15
Long-Stop Date for the Minimum Completion Requirement (empty)