Centrica Brigg Power Station, Scawby Brook, Brigg DN20 9LT. - Centrica Brigg Power Station is an Open Cycle Gas Turbine (OCGT) electricity generating station.

Component ID: EBRGG3
Last updated: 01 Aug 2025 19:06 UTC
CMU ID:
Description:
Centrica Brigg Power Station is an Open Cycle Gas Turbine (OCGT) electricity generating station.
Auction:
2018-19 (T-1) One Year Ahead Capacity Auction

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 95.38
  • Connection Capacity (CMU Registry) 100.60 MW
  • Anticipated Capacity (CMU Registry) 93.86 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name CBS ENERGY STORAGE ASSETS UK LIMITED
  • Parent Company (CMU Registry) Centrica plc
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4407789571247

Field Value
_id 589548
Type T-1
rank 0.0573088
CMU ID EBRGG3
Auction Name 2018-19 (T-1) One Year Ahead Capacity Auction
Component ID E_BRGG-1
Delivery Year 2018
De-Rated Capacity (empty)
OS Grid Reference SE 991 059
Proven DSR Capacity (empty)
Location and Post Code Centrica Brigg Power Station, Scawby Brook, Brigg DN20 9LT.
Connection / DSR Capacity (empty)
Primary Fuel of Component (empty)
Generating Technology Class OCGT and Reciprocating Engines (Fuel Type - Gas)
Description of CMU Components Centrica Brigg Power Station is an Open Cycle Gas Turbine (OCGT) electricity generating station.
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 5438
Type T-4
CMU ID EBRGG3
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2021-22 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Brigg OCGT
CM Unit Type CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2021
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company Centrica plc
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category Existing Generating CMU
Storage Facility No
De-Rated Capacity 95.375
Name of Applicant CBS ENERGY STORAGE ASSETS UK LIMITED
Primary Fuel Type Gas
Registered Holder CBS ENERGY STORAGE ASSETS UK LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate Β£5000.00 /MW
Termination Fee 2 Rate Β£25000.00 /MW
Termination Fee 3 Rate Β£10000.00 /MW
Termination Fee 4 Rate Β£15000.00 /MW
Termination Fee 5 Rate Β£35000.00 /MW
Connection / DSR Capacity 100.596
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary 01/10/2021 - 30/09/2022:0.000 MW
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2021-EBRGG3-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 93.862
Term of the Capacity Agreement 1
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2021-03-30
List of Traded Capacity Obligations T1: 10.368 MW; T2: 12.536 MW; T3: 5.495 MW; T4: 3.730 MW; T5: 4.565 MW; T6: -6.482 MW; T7: -1.287 MW; T8: -1.106 MW; T9: -1.869 MW; T10: -6.250 MW; T11: -2.886 MW; T12: -6.120 MW; T13: -1.152 MW; T14: -1.044 MW; T15: -1.044 MW; T16: -7.454 MW
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation (empty)
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies T1: 01/10/2021 - 30/09/2022; T2: 01/10/2021 - 30/09/2022; T3: 01/10/2021 - 30/09/2022; T4: 01/10/2021 - 30/09/2022; T5: 01/10/2021 - 30/09/2022; T6: 01/10/2021 - 30/09/2022; T7: 01/10/2021 - 30/09/2022; T8: 01/10/2021 - 30/09/2022; T9: 01/10/2021 - 30/09/2022; T10: 01/10/2021 - 30/09/2022; T11: 01/10/2021 - 30/09/2022; T12: 01/10/2021 - 30/09/2022; T13: 01/10/2021 - 30/09/2022; T14: 01/10/2021 - 30/09/2022; T15: 01/10/2021 - 30/09/2022; T16: 01/10/2021 - 30/09/2022
Secondary Trading Contact - Telephone '+4407789571247
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2021/2022
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 1
Long-Stop Date for the Minimum Completion Requirement (empty)