Veolia Recycling and Energy Recovery Facility Newmarket Approach Leeds LS9 0RJ - Recycling and Energy Recovery Facility (RERF) at Former Wholesale Market Site Newmarket Approach Leeds LS9 0RJ. Station commenced operation in November 2015. RERF capacity 20.5 tonnes per hour. RERF consists of municipal waste burning grate; steam production; generation of electricity at 11kV via steam turbine generator. The power factor for this CMU is 0.95.

Component ID: LEED02
Last updated: 27 Jul 2025 04:44 UTC

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 11.70
  • Connection Capacity (CMU Registry) 13.46 MW
  • Anticipated Capacity (CMU Registry) 11.70 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name VEOLIA UK LIMITED
  • Parent Company (CMU Registry) N/A
  • Secondary Trading Email (CMU Registry) N/A
  • Secondary Trading Phone (CMU Registry) +4402078125000

Field Value
_id 585910
Type T-1
rank 0.0706241
CMU ID LEED02
Auction Name 2017-18 (T-1) One Year Ahead Capacity Auction
Component ID LEED02
Delivery Year 2017
De-Rated Capacity (empty)
OS Grid Reference SE 326 326
Proven DSR Capacity (empty)
Location and Post Code Veolia Recycling and Energy Recovery Facility Newmarket Approach Leeds LS9 0RJ
Connection / DSR Capacity (empty)
Primary Fuel of Component (empty)
Generating Technology Class (empty)
Description of CMU Components Recycling and Energy Recovery Facility (RERF) at Former Wholesale Market Site Newmarket Approach Leeds LS9 0RJ. Station commenced operation in November 2015. RERF capacity 20.5 tonnes per hour. RERF consists of municipal waste burning grate; steam production; generation of electricity at 11kV via steam turbine generator. The power factor for this CMU is 0.95.
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 4283
Type T-4
CMU ID LEED02
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2020-21 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Leeds ERF
CM Unit Type Non CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2020
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company (empty)
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category Existing Generating CMU
Storage Facility No
De-Rated Capacity 11.7
Name of Applicant VEOLIA UK LIMITED
Primary Fuel Type (empty)
Registered Holder VEOLIA UK LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate Β£5000.00 /MW
Termination Fee 2 Rate Β£25000.00 /MW
Termination Fee 3 Rate Β£10000.00 /MW
Termination Fee 4 Rate Β£15000.00 /MW
Termination Fee 5 Rate Β£35000.00 /MW
Connection / DSR Capacity 13.461
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2020-LEED02-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 11.7
Term of the Capacity Agreement 1
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email (empty)
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2017-01-20
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 11.7
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+4402078125000
Capacity Agreement has been Terminated Yes
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2020/2021
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement 2017-08-14
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round (empty)
Long-Stop Date for the Minimum Completion Requirement (empty)