7 unique locations (444 components)

1 Thane Road West, Nottingham, NG2 3AA (125 components)
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
• One of three CHP units at 1 Thane Road West, Nottingham, NG2 3AA
• One of three CHP units at 1 Thane Road West, Nottingham, NG2 3AA.
Active • 2025-26 (T-4), 2024-25 (T-1) ...
101.02 MW
Aston University, Aston Triangle, Birmingham, West Midlands, B4 7ET (57 components)
• 1MW Combined heat and Power Plant at Aston University. Total Capacity is 3.000MW, consisting of two generators - 2.000MW and 1.000MW
• 2MW Combined heat and Power Plant at Aston University. Total Capacity is 3.000MW, consisting of two generators - 2.000MW and 1.000MW
• Containerised high speed gas-fired reciprocating engines with transformers, switchgear and associated control gear with a total connection capacity of 9MW.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
13.92 MW
Mitchell Road, Phoenix Parkway, Corby, Northamptonshire, NN17 5QT (45 components)
• The CMU is a Open Cycle Gas Turbine (OCGT)
• The CMU is a combined cycle gas turbine
• The CMU is a gas plant, capable of running in either OCGT or CCGT modes
Active • 2028-29 (T-4), 2026-27 (T-4) ...
2527.80 MW
Power Station Road Isle of Grain Rochester ME3 0AR (69 components)
• Grain B CCGT Unit 6 Grain B power station provides heat to the Grain LNG regasification facility.
• OCGT from Grain U1. Fuel is Diesel as specified in BS EN590
• OCGT from Grain U4. Fuel is Diesel as specified in BS EN590
Active • 2028-29 (T-4), 2027-28 (T-4) ...
2886.91 MW
Royal South Hants Hospital, Graham Road, Southampton, Hampshire, SO14 0YG (23 components)
• 0.725MW Combined Heat and Power Plant Royal South Hants Hospital
• Component has yet to be procured.
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
Active • 2025-26 (T-4), 2024-25 (T-4) ...
47.83 MW
SIMEC Lochaber Power Lochaber Smelter North Road Fort William PH336TH (65 components)
• Hydro power turbine generator Unit 1 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
• Hydro power turbine generator Unit 3 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
• Hydro power turbine generator Unit 5 of the Lochaber Smelter hydro power plant, connected to a private network which in turn is connected to the local distribution network. The MPANs relate to the connection of the private network to the distribution network only. They will not be used for settlement purposes. Instead this CMU component will use bespoke net metering.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
443.26 MW
Staythorpe Power Station Staythorpe Newark Nottinghamshire NG23 5PS (60 components)
• Staythorpe 1 - CCGT MSID: 7210
• Staythorpe 2 - CCGT MSID: 7210
• Staythorpe 4 - CCGT MSID: 7210
Active • 2028-29 (T-4), 2027-28 (T-4) ...
6050.24 MW
Loading map...
Showing 7 locations