Home Technologies Companies Locations Map Explorer FAQ Trading Board ChatGPTChatGPT Buy Me A Coffee Help Login Register
Theme
Light Dark Auto
Quick Menu
Loading...
Loading...

Combined Heat and Power (CHP)

346 unique locations (3777 components) - Page 5 of 14

Energy Centre, Lower Mosley Street, Manchester M2 3GX (9 components)

A 3.36MW gas fired reciprocating engine CHP.

Active • 2024-25 (T-4), 2023-24 (T-1) ...
5.97 MW
Energy Centre, Northwick Park Hospital, Watford Road, London, HA1 3UJ (1 component)

VIT42A - CHP unit at Energy Centre, Northwick Park Hospital, Watford Road, London, HA1 3UJ

Active • 2025-26 (T-4)
Energy Centre, Quarryfield Road, Gateshead NE8 3BE (16 components)
• 1 x 2MW CHP generator; natural gas reciprocating engine; primary fuel type = natural gas
• 1x2MW CHP generator: natural gas reciprocating engine. Primary fuel type = natural gas
• CHP in a district heating environment, providing heat & electricity to local area and exporting excess.
Inactive • 2020-21 (T-4), 2019-20 (T-1) ...
Energy Centre, St James's University Hospital, Beckett Street, Leeds, LS9 7TF. (7 components)

4.5MWe combined heat and power (CHP) natural gas fired reciprocating engine.

Inactive • 2023-24 (T-4), 2022-23 (T-3) ...
Energy Centre Westfield London, Ariel Way, White City, London, W12 7GF (26 components)

A gas engine CHP site providing electricity & heat to the associated development (3)

Active • 2028-29 (T-4), 2027-28 (T-4) ...
Energy Facilities Building, Walsgrave Hospital, Clifford Bridge Road, Coventry, CV2 2DX (8 components)
• VIT303 - CHP unit at Energy Facilities Building, Walsgrave Hospital, Clifford Bridge Road, Coventry, CV2 2DX
• VIT503 - CHP unit at Energy Facilities Building, Walsgrave Hospital, Clifford Bridge Road, Coventry, CV2 2DX
Active • 2024-25 (T-4), 2023-24 (T-1) ...
6.03 MW
Energy Hub, Corner of Rodney Road and Heygate Street, London, SE17 1FJ (18 components)
• A site with two gas engine CHPs providing hot water to a local district heating network
• A site with two gas engine CHPs, providing hot water to a local district heating network
Active • 2028-29 (T-4), 2027-28 (T-4) ...
Engie Great Coates, Grimsby, DN31 2TT (28 components)

Combined Heat and Power Plant Grimsby made up of 5 generators totalling 30MW however the export capacity is limited to 6.MW (other generators are on site are defunct) so the …

Active • 2024-25 (T-1), 2023-24 (T-1) ...
2.05 MW
Engie Great Coates, Grimsby, DN31 2TT (19 components)
• Combined Heat and Power Plant Grimsby made up of 5 generators totalling 30MW however the export capacity is limited to 6.MW (other generators are on site are defunct) so the participating generator sizes have been inserted pro rata to achieve the overall CMU capacity of 5.943 MW as per the 3 highest export peaks
• Combined Heat and Power Plant Grimsby made up of 5 generators totalling 30MW however the export capacity is limited to 6.MW (other generators are on site are defunct) so the participating generator sizes have been inserted pro rata to achieve the overall CMU capacity of 5.943 MW as per the 3 highest export peaks.
Active • 2024-25 (T-1), 2023-24 (T-1) ...
2.05 MW
Esso Petroleum Company,Limited, Oil Refinery at Esso Refinery - Fawley - Southampton - Hampshire - SO45 1TX - United Kingdom (10 components)
• Unit 5 is a Cogenation unit which produces both steam and power. Unit 5 is the largest generating unit at Fawley refinery. This Generating Unit forms the 'E_FAWN-1' BMU on its own and is part of the larger site inclusive BM Trading Unit, 'EPCO1'. All Components of EMG-19, EMD-19 are located within the physical boundaries of the Esso Petroleum Company,Limited, Oil Refinery at Esso Refinery - Fawley - Southampton - Hampshire - SO45 1TX - United Kingdom. Unit 5 is one of three power and steam generation units on site and is a Gas Turbine CHP plant. It is connected to the Local Distribution Network (LDN) at 132kV level at the Fawley North Sub-Station (MSID 7081). Unit 5 is a licensed generator. Unit 5 has various auxiliary load equipment- the power for which is supplied from another part of the LDN Fawley North Sub-Station. This auxiliary power has half hourly meters installed. The two auxiliary meters have the IDs: R98HAN757 (aka S36A-VFH-TR01) and R98HAN758 (aka S36A-VFH-TR02). Gross 3 HH av. peak generation from Unit 5 on separate days = 141.040 MW At these three HH times, aux load on Unit 5 = 2.597 MW Net generation from Unit 5 = 138.443 MW
• Unit 5 is a Cogenation unit which produces both steam and power. Unit 5 is the largest generating unit at Fawley refinery. This Generating Unit forms the 'E_FAWN-1' BMU on its own and is part of the larger site inclusive BM Trading Unit, EPCO1. All Components of EMG-18, EMD-U3 and EMD-T1 are located within the physical boundaries of the Esso Petroleum Company,Limited, Oil Refinery at Esso Refinery - Fawley - Southampton - Hampshire - SO45 1TX - United Kingdom. Unit 5 is one of three power and steam generation units on site and is a Gas Turbine CHP plant. It is connected to the Local Distribution Network (LDN) at 132kV level at the Fawley North Sub-Station (MSID 7081). Unit 5 is a licensed generator. Unit 5 has various auxiliary load equipment- the power for which is supplied from another part of the LDN Fawley North Sub-Station. This auxiliary power has half hourly meters installed. Gross 3 HH av. peak generation from Unit 5 on separate days = 139.707 MW At these three HH times, aux load on Unit 5 = 2.517 MW Net generation from Unit 5 = 137.190 MW
• Unit 5 is a Cogeneration unit which produces both steam and power. Unit 5 is the largest generating unit at Fawley refinery. This Generating Unit forms the 'E_FAWN-1' BMU on its own and is part of the larger site inclusive BM Trading Unit, 'EPCO1'. All Components of EMG244 are located within the physical boundaries of the Esso Petroleum Company,Limited, Oil Refinery at Esso Refinery - Fawley - Southampton - Hampshire - SO45 1TX - United Kingdom. Unit 5 is one of three power generation units on the site and is a Gas Turbine CHP plant. It is connected to the Local Distribution Network (LDN) at 132kV level at the Fawley North Sub-Station (MSID 7081). Unit 5 is a licensed generator. Unit 5 has various auxiliary load equipment, the power for which is supplied from another part of the LDN Fawley North Sub-Station. This auxiliary power has half hourly meters installed. The two auxiliary meters have the IDs: R98HAN757 (aka S36A-VFH-TR01) and R98HAN758 (aka S36A-VFH-TR02).
Active • 2028-29 (T-4), 2027-28 (T-4) ...
126.55 MW
Esso Refinery - Fawley - Southampton - Hampshire - SO45 1TX - United Kingdom (32 components)
• TG1B is part of the aggregated CMU EMD-20, which is made up of 2 Generating Units of which TG1B is the larger. This Generating Unit is embedded in the 'E_FAWND' BMU and is part of the larger site inclusive BM Trading Unit, 'EPCO1'. All Components of 'EMD-20' are located within the physical boundaries of the Esso Petroleum Company,Limited Oil Refinery at Esso Refinery - Fawley - Southampton - Hampshire - SO45 1TX - United Kingdom. TG1B is one of three power generation units on the site and is a Steam Turbine plant. It is connected to the Local Distribution Network (LDN) at 132kV level at the Fawley North Sub-Station (part of MSID 7095). Both Unit 3 and TG1B units share various auxiliary load equipment- the power for which is supplied from another part of the LDN Fawley North Sub-Station. Installation of separate metering for the auxiliary power for both TG1B and Unit 3 has been completed providing half hourly meters for the auxiliary load for the two units. Due to the large amount of common equipment shared by the two generation units (TG1B and Unit 3) we are unable to determine exactly what part of the auxiliary load is directly attributable to TG1B and thus for this CMU we have attributed the auxiliary load between the two. The auxiliary meters for Unit 3 and TG1B combined are: TR1MWI_MAIN, TR2MWI_MAIN and 26AMWI_MAIN. This entire metering configuration has been successfully assessed and tested. To clarify the 3 units within the refinery boundary, they are Unit 5 (EMG-20) and TG1B and Unit 3 (which make up EMD-20). Gross 3 HH av. peak generation from TG1B on separate days = 49.863 MW At these three HH times, aux load on TG1B = -1.468 MW Net generation from TG1B = 48.394 MW The 48.394MW described above is the historical proven capacity. However, based on the planned future availability of this unit, we wish to submit a conservative 18MW connection capacity. To clarify the numbers provided in the application page are in half hourly periods, as the units specified were MWh and therefore reporting half hourly period was required.
• TG1B is part of the aggregated CMU EMD244, which is made up of 2 Generating Units of which TG1B is the larger. This Generating Unit is embedded in the 'E_FAWND' BMU and is part of the larger site inclusive BM Trading Unit, 'EPCO1'. All Components of 'EMD244' are located within the physical boundaries of the Esso Petroleum Company,Limited Oil Refinery at Esso Refinery - Fawley - Southampton - Hampshire - SO45 1TX - United Kingdom. TG1B is one of three power generation units on the site and is a Steam Turbine plant. It is connected to the Local Distribution Network (LDN) at 132kV level at the Fawley North Sub-Station (part of MSID 7095). Both Unit 3 and TG1B units share various auxiliary load equipment, the power for which is supplied from another part of the LDN Fawley North Sub-Station. Installation of separate metering for the auxiliary power for both TG1B and Unit 3 has been completed providing half hourly meters for the auxiliary load for the two units. Due to the large amount of common equipment shared by the two generation units (TG1B and Unit 3) we are unable to determine exactly what part of the auxiliary load is directly attributable to TG1B and thus for this CMU we have attributed the auxiliary load between the two. The auxiliary meters for Unit 3 and TG1B combined are: TR1MWI_MAIN, TR2MWI_MAIN and 26AMWI_MAIN. This entire metering configuration has been successfully assessed and tested.
• Unit 3 is part of the aggregated CMU EMD-20, which is made up of 2 Generating Units of which Unit 3 is the smallest. This Generating Unit is embedded in the ?E_FAWND? BMU and is part of the larger site inclusive BM Trading Unit, ?EPCO1?. All Components of ?EMD-20? are located within the physical boundaries of the Esso Petroleum Company,Limited Oil Refinery at Esso Refinery - Fawley - Southampton - Hampshire - SO45 1TX - United Kingdom. Unit 3 is one of three power generation units on site and is a Gas Turbine CHP plant. It is connected to the Local Distribution Network (LDN) at 132kV level at their Fawley North Sub-Station (part of MSID 7095). Both units share various auxiliary load equipment- the power for which is supplied from another part of the LDN Fawley North Sub-Station. Installation of separate metering for the auxiliary power for both TG1B and Unit 3 has been completed providing half hourly meters for the auxiliary load for the two units. Due to the large amount of common equipment shared by the two generation units (TG1B and Unit 3) we are unable to determine exactly what part of the auxiliary load is directly attributable to Unit 3 and thus for this CMU we have attributed the auxiliary load evenly about the three units - i.e. 7.954/3 = 2.6513% of MSID 7096, thus 2.024 MW. (NB. the rest of MSID 7095 is made up of one of our other components of our CMU i.e. TG1B). Due to the large amount of common equipment shared by the two generation units (TG1B and Unit 3) we are unable to determine exactly what part of the auxiliary load is directly attributable to TG1B and thus for this CMU we have attributed the auxiliary load between the two. The auxiliary meters for Unit 3 and TG1B combined are: TR1MWI_MAIN, TR2MWI_MAIN and 26AMWI_MAIN. This entire metering configuration has been successfully assessed and tested. Gross 3 HH av. peak generation from Unit 3 on separate days = 32.869 MW At these three HH times, aux load on Unit 3 = -1.468 MW Net generation from Unit 3 = 31.401 MW The 31.401MW described above is the historical proven capacity. However, based on the planned future availability of this unit, we wish to submit a conservative 18MW connection capacity. To clarify the numbers provided in the application page are in half hourly periods, as the units specified were MWh and therefore reporting half hourly period was required.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
77.27 MW
Estates & Facilities, North Devon District Hospital, Raleigh Park, Barnstaple, EX31 4JB (2 components)

1 x gas reciprocating engine with a total rated gross power capacity of 0.800 MW (2)

Active • 2028-29 (T-4), 2025-26 (T-1)
1.45 MW
Europa Energy Centre, Hills Court Road, Ash, Kent, CT3 2AP (21 components)
• The CMU Component will have a connection capacity of 15MW. Gas-fired reciprocating engine will be the technology used.
• The CMU component BREH01 consists of one CHP engine supplying heat, CO2 and power to the on site Nursery.
• The CMU component BREH02 consists of one CHP engine supplying heat, CO2 and power to the on-site Nursery.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
41.65 MW
Excel Energy Centre Warehouse R Royal Victoria Dock Northside London E16 1BA (29 components)
• 1.2 MW Combined Heat and Power Engine.
• 1.6 MW Combined Heat and Power Engine
• 1.6MW Combined Heat and Power Engine
Active • 2028-29 (T-4), 2027-28 (T-4) ...
2.55 MW
Fellside CHP Sellafield Ltd Seascale Cumbria CA20 1PG UK (5 components)

Fellside CHP is located in Seascale- Cumbria- UK and consists of three GE Frame 6581B gas turbines which are able to run on natural gas or distillate. The primary purpose …

Inactive • 2022-23 (T-4), 2021-22 (T-4) ...
Fielding & Johnson Building University Of Leicester University Road LEICESTER Leicestershire LE1 7RH (30 components)
• Combined Heat and Power Plant, University of Leicester, capacity of generator 1.600MW (2)
• Combined Heat and Power Plant, University of Leicester, generator's capacity 1.600MW
Active • 2028-29 (T-4), 2027-28 (T-4) ...
57.65 MW
Foresterhill Health Campus, Aberdeen AB25 2AY (6 components)

A gas turbine installed at Aberdeen Royal Infirmary

Inactive • 2023-24 (T-4), 2022-23 (T-3) ...
Frimley Park Hospital, Portsmouth Road, GU16 7UJ (5 components)
• CHP generating in NHS hospital. No aux load.
• CHP generating to cover site load, which exceeds generating capacity. No aux load.
Inactive • 2022-23 (T-4), 2019-20 (T-1) ...
Galley Hill Road Waltham Abbey Essex EN9 2AG (16 components)
• Gas CHP engines 1.37MW and 1.50MW. Primary fuel type = Natural Gas
• Gas engines in commercial horticultural environment with no auxilliary load. All generation unit capacities are nominal and allow for site-specific variations
Active • 2028-29 (T-4), 2025-26 (T-4) ...
2.50 MW
George Square Charles St Lane EH8 9AG (3 components)

CHP generating for site load, which exceeds generating capacity. No aux load.

Inactive • 2022-23 (T-4), 2019-20 (T-1)
GMV Energy Centre, 3-5 PEARTREE WAY, LONDON, SE10 0GY (6 components)

A gas engine CHP site providing hot water to a local district heating network

Active • 2028-29 (T-4), 2027-28 (T-4) ...
Good Hope Hospital, Rectory Road, Sutton Coldfield, West Midlands, B75 7RR (2 components)

1 x gas engine with a total rated gross power capacity of 1.166 MW.

Active • 2028-29 (T-4), 2025-26 (T-1)