DSR (Demand Side Response)

5 unique locations (38 components)

BS23 0AP (11 components)
• Containerised High Speed Gas-fired reciprocating engines with transformers, switchgear and associated control gear with a total connection capacity of 8.99MW.
• Existing CCGT unit
• Water treatment centre
Inactive • 2022-23 (T-4), 2022-23 (T-3) ...
Campus Data Centre, Spring Way, Hemel Hempstead, Herts, HP2 7SU (2 components)
• DSR component offering flexibility delivered by load turn down at a data centre
• New build power station comprised of multiple reciprocating engines.
Inactive • 2022-23 (T-4), 2021-22 (T-4)
CAULDON LOW QUARRY, CAULDON, STOKE ON TRENT, STAFFORDSHIRE, ST10 3EW (8 components)
• EnerG 1000 CHP
• The CMU Component reduces import demand by turning off equipment and other non-essential loads.
Inactive • 2023-24 (T-4), 2021-22 (T-4) ...
21.54 MW
Land to the West of Chapterhouse Close, Ellesmere Port, CH65 4EL (3 components)
• 49.9 MW Gas Reciprocating Engines envisaged to be made up of multiple modules.
• Office site with behind the meter bio-diesel generation - offsetting site load and exporting surplus
Inactive • 2023-24 (T-4), 2021-22 (T-4)
47.40 MW
Southdownview Way, Worthing, West Sussex, BN14 8QH (14 components)
• CHP and autogeneration
• DSR component providing load turn-down at a paper product manufacturing site
Inactive • 2023-24 (T-4), 2022-23 (T-4) ...
6.35 MW
Loading map...
Showing 5 locations