8 unique locations (39 components)

Coatbridge, ML5 4UG, Scotland (3 components)

Energy from Waste facility

Inactive • 2023-24 (T-4), 2022-23 (T-4) ...
Ferrybridge MFE Limited Kirkhaw Lane Off Stranglands Lane Knottingley West Yorkshire WF11 8DX (2 components)

FM1 is a twin boiler, single steam turbine energy from waste plant exporting at 132kV to the NPG area network.

Inactive • 2022-23 (T-4), 2021-22 (T-4)
Lister Road Dudley West Midlands DY2 8JT (6 components)
• 2 stream Municipal waste incinerator: Total installed capacity 7.3MW, DNC 6.2MW
• 2 stream Municipal waste incinerator: Total installed capacity 7.4MW, DNC 6.3MW. We have added covering letters on the following, change in registered address for DWS as shown in the connection agreement, confirmation of the location of the CMU and confirmation on the new name for Midland Electricity (named party on the Connection Agreement)
Inactive • 2021-22 (T-4), 2019-20 (T-1) ...
Newlands Road Wentloog Cardiff CF3 2EF (2 components)

Energy From Waste facility

Inactive • 2023-24 (T-4), 2021-22 (T-4)
North Road, Eastham, CH65 1AJ (4 components)

Energy from waste Facility

Inactive • 2023-24 (T-4), 2022-23 (T-4) ...
Stoke EfW plant Campbell Road Sideway Stoke on Trent St4 4DX (8 components)
• 2 stream municipal waste incinerator
• 2 stream municipal waste incinerator generating electricity through one turbine generator. Electricity is used on site with the excess being sold onto the grid. We have added covering letters on the following, change in registered address for HWS as shown in the connection agreement, confirmation of the location of the CMU and confirmation on the new name for Midland Electricity (named party on the Connection Agreement)
Inactive • 2023-24 (T-4), 2022-23 (T-4) ...
Wolverhampton EfW Crown Street West Midlands WV1 1QB (5 components)
• 2 stream municipal waste incinerator. Total Installed capacity 8.7MW, DNC 7.3MW. We have added covering letters on the following, change in registered address for WWS as shown in the connection agreement, confirmation of the location of the CMU and confirmation on the new name for Midland Electricity (named party on the Connection Agreement)
• 2 stream municipal waste incinerator. Total Installed capacity 8.7MW, DNC 8.35MW
Inactive • 2021-22 (T-4), 2019-20 (T-1) ...
Loading map...
Showing 8 locations