Onshore Wind

7 unique locations (235 components)

West Marsh Road Spalding Lincolnshire PE11 3BB (16 components)
• Battery storage located at Drayton Manor Farm, Alcester Road, Stratford-Upon-Avon, CV37 9RG with a nameplate capacity of 1.000 MW. Connection capacity is calculated as the Average Output of the Existing Generating CMU over 3 settlement periods identified over the previous months, per Capacity Market rules 3.5.3 & 3.5.4.
• Kiln Power is a 16 MW power plant comprising gas reciprocating engines. The export of the power plant is connected to the local distribution network via two separately metered 8MW connections (of which this is one of the two CMU components) and it is connected to the local gas network. Kiln Power has a single Balancing Service ID - NGSTORKILN218. To distinguish between the two components of the CMU a numbering system has been used. The two components are separately metered.
• Wind Turbines to be installed at Crossdykes Wind Farm
Active • 2027-28 (T-4), 2024-25 (T-4) ...
255.05 MW
St Asaph Power, Glascoed Road, St Asaph, Denbighshire LL17 0LQ (15 components)
• 13-turbine wind farm located in Lanark, Scotland with the installed capacity of 45.000MW
• 16 MW power plant comprising of reciprocating engines.The Power plant is connected to the local distribution and gas network.
• 16MW Power plant comprising reciprocating engines. The Power plant is connected to the local distribution and gas network.
Active • 2028-29 (T-4), 2025-26 (T-4) ...
44.63 MW
Power Station Road Isle of Grain Rochester ME3 0AR (69 components)
• Grain B CCGT Unit 6 Grain B power station provides heat to the Grain LNG regasification facility.
• OCGT from Grain U1. Fuel is Diesel as specified in BS EN590
• OCGT from Grain U4. Fuel is Diesel as specified in BS EN590
Active • 2028-29 (T-4), 2027-28 (T-4) ...
2886.91 MW
Park Farm Barn, Chichester Rd, Selsey, Chichester PO20 9HP, United Kingdom (58 components)
• A Packaged 3.976MW, 11kV natural gas fired reciprocating engine CHP
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms.
• Wind Turbine Generators x 15
Active • 2028-29 (T-4), 2027-28 (T-4) ...
64.94 MW
Northfleet Mill, Crete Hall Road, Gravesend, DA11 9AD (18 components)
• 13-turbine wind farm located in Lanark, Scotland with the installed capacity of 45.000MW
• Containerised High Speed Gas-fired reciprocating engines with transformers, switchgear and associated control gear with a total connection capacity of 5MW
• Paper Mill carrying out DSR using load turn-down.
Active • 2028-29 (T-4), 2025-26 (T-4) ...
33.39 MW
Knapton Generating Station, East Knapton, Malton, YO17 8JF (2 components)
• 12-turbine wind farm located in Scotland with the installed capacity of 43.200MW
• Natural gas fired reciprocating engines installed upon designated land within the existing Knapton Generating Station facility. The CMU output will have a combined total output of 40.9 MWe.
Active • 2027-28 (T-4), 2024-25 (T-4)
41.95 MW
Carrington Power Station 132 Manchester Road Carrington Manchester M31 4AY United Kingdom (57 components)
• CMU component consisting of multiple battery cells for electricity storage @ 400V and the supply of electricity to the 400V network
• The CMU component is a combined cycle gas turbine
• one CHP (1.9MW rating) in a horticulatural environment with no aux load
Active • 2028-29 (T-4), 2027-28 (T-4) ...
3488.59 MW
Loading map...
Showing 7 locations