1020 Slutchers Lane, Centre Park, Warrington, WA1 1QL (9 components)
• 16 MW power plant comprising 8 x 2MW gas reciprocating engines. The power plant is connected to the local distribution network and local gas network.
• 16 MW power plant comprising gas reciprocating engines. The power plant is connected to the local distribution network and local gas network.
• 16MW Power plant comprising reciprocating engines. The Power plant is connected to the local distribution and gas network.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
14.77 MW
132 Manchester Road, Carrington, Manchester, M31 4AY (17 components)
• 5 x 4.5MW Gas Reciprocating engines with all ancillary equipment to be installed on the Trafford Power Site
• 5 x 9.98MW Gas Reciprocating engines with all ancillary equipment to be installed on the Trafford Power Site
• One 4.5MW Gas Reciprocating engine with all ancillary equipment to be installed on the Trafford Power Site
Active • 2027-28 (T-4), 2025-26 (T-4) ...
93.41 MW
1A Elms Farm Industrial Estate Edison Road Bedford Bedfordshire MK41 0HU (16 components)

Containerised High Speed Gas-fired reciprocating engines with transformers, switchgear and associated control gear with a total connection capacity of 5MW.

Active • 2027-28 (T-4), 2026-27 (T-4) ...
4.72 MW
23 Whittle Road, Ferndale Industrial Estate, Wimborne, BH21 7PW (6 components)

CMU consisting of multiple reciprocating engines and alternators

Active • 2025-26 (T-4), 2024-25 (T-1) ...
4.83 MW
25 Rookwood Way, Haverhill, CB9 8PB (1 component)

New Build Generating CMU comprising of gas fuelled reciprocating engines and gas delivery plant

Active • 2025-26 (T-4)
2 South Wardpark Place, Wardpark, Cumbernauld, Glasgow, North Lanarkshire, G67 3HX (33 components)
• New build gas generator
• Operational Reciprocating Engine
• Operational gas reciprocating engine.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
7.48 MW
40 Gardiner Road, Edinburgh, Midlothian, EH4 3RN (1 component)

New build power station comprised of multiple reciprocating engines.

Active • 2025-26 (T-4)
46 Station Road Stokesley Middlesbrough TS9 7AA (12 components)
• 2 x 2.25 Gas reciprocating engines to be installed at Cleveland Nurseries (replacing existing CHP)
• Gas CHP engines in commercial horticultural usage with no auxilliary load
Active • 2027-28 (T-4), 2025-26 (T-4) ...
4.25 MW
4 Chemistry Ln, Pentre, Deeside CH5 2DA, UK (4 components)

14MW power plant comprising of reciprocating engines. The power plant is connected to the local distribution network and local gas network.

Active • 2027-28 (T-4), 2026-27 (T-4) ...
13.02 MW
4 Finway Road Hemel Hempstead HP2 7PT (16 components)

Containerised High Speed Gas-fired reciprocating engines with transformers, switchgear and associated control gear with a total connection capacity of 5MW

Active • 2027-28 (T-4), 2026-27 (T-4) ...
4.72 MW
62 Marlborough Road Lancing Business Park Lancing BN15 8UF (3 components)

CMU consisting of multiple reciprocating engines and alternators

Active • 2025-26 (T-4), 2022-23 (T-1)
84 Bridge St, Wednesbury WS10 0AN (1 component)

New build power station comprised of multiple reciprocating engines

Active • 2025-26 (T-4)
Aberaman Industrial Estate (South Bound), Aberaman, Nr Aberdare, Rhondda Cynon Taff, CF44 6DA (19 components)
• The CMU will be formed of multiple individual gas generating units controlled centrally and exporting to the distribution system.
• The CMU will be formed of multiple individual generating units controlled centrally and exporting to the distribution system.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
9.35 MW
Adjacent to Seal Sand Bulk Storage Facility Seal Sands Stockton-on-Tees Cleveland TS2 1UB (8 components)
• Existing OCGT
• The auxiliary load is minimal (1MW) and have been removed from the metering assessment when calculating the maximum generating output.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
APS Growers Ltd / Branfield Nursery 111 Stockbridge Road Elloughton HU15 1HW (16 components)
• One Jenbacher CHP engine with a generation capacity of 3.36 MW
• The new Energy Centre will consist of one Jenbacher CHP engine with a generation capacity of 3.36 MW and a thermal output of 3.984 MW.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
3.12 MW
Arlesey Landfill Site Mill Lane Arlesey Bedfordshire SG15 6RF (15 components)
• Gas reciprocating engines
• The system comprises of two gas reciprocating engines provided an exported output of around 2MW.
Active • 2027-28 (T-4), 2026-27 (T-4) ...
2.97 MW
Aveley Landfill Site Sandy Lane Aveley RM15 4XP (17 components)
• 4x gas reciprocating engines with a combined output of approximately 4.3MW. All associated gas delivery equipment and switchgear is included. The generating units are connected to the distribution network.
• Gas fired generating units
• Gas reciprocating engines
Active • 2027-28 (T-4), 2026-27 (T-4) ...
0.92 MW
Batleys Cash and Carry Gielgud Way Coventry CV2 2SZ (11 components)

A completed power plant, with associated civil works, switchgear and electrical connection.

Active • 2028-29 (T-4), 2027-28 (T-4) ...
5.61 MW
Batleys Cash and Carry Talbot Road Fareham PO15 5RY (11 components)
• The CMU component is net of the auxiliary power required (2)
• A completed power plant, with associated civil works, switchgear and electrical connection.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
18.45 MW
Belvedere Lane, Milton Keynes, MK17 9JH (2 components)
• 3 x 2MW Gas fuelled generator units to be installed on designated land within a compound at Belvedere Nurseries
• Grid-scale energy storage system based on Lithium Ion, capable of exporting 8MW for a 1 hour duration installed on designated land within a compound at Belvedere Nurseries
Active • 2025-26 (T-4)
Bond Avenue Bletchley Milton Keynes MK1 1JJ (19 components)

The CMU component comprises of three 2MW Reciprocating Gas Engines

Active • 2028-29 (T-4), 2027-28 (T-4) ...
11.83 MW
Bones lane, Cheddleton, Leek, Staffordshire, ST13 7BT (7 components)

1.9 MW Gas gen ENER-G 1999

Active • 2025-26 (T-4), 2024-25 (T-4) ...
Booker Cash and Carry Didcot OX11 7HJ (7 components)

A completed power plant, with associated civil works, switchgear and electrical connection.

Active • 2026-27 (T-4), 2025-26 (T-4) ...
3.14 MW