118 unique locations (1213 components) - Page 1 of 5

Worset Lane, Hartlepool, TS27 3BQ (6 components)

A new build, gas fuelled generation station (2)

Active • 2028-29 (T-4), 2027-28 (T-4)
92.98 MW
Woodhouse Energy Centre A. Pearson and Sons? Nursery Alderley Edge SK9 7UW (13 components)
• The CMU Component will have a connection capacity of 3.376MW. Gas-fired reciprocating engine will be the technology used.
• The CMU component is installed in the Woodhouse Energy Centre that is located at a Nursery site in Alderley Edge.
• The CMU component, CASQ17 supplies heat, CO2 and electricity to the onsite nursery and facilities.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
3.08 MW
Wolverhampton Power, Northern Steel Rocks, Cross Street, Wolverhampton, WV1 2HS (16 components)
• 16 MW power plant comprising 8 x 2MW gas reciprocating engines. The power plant will be connected to the local distribution network and local gas network.
• 16 MW power plant comprising reciprocating engines. The power plant is connected to the local distribution network and local gas network.
• 16MW Power plant comprising reciprocating engines. The Power plant is connected to the local distribution and gas network.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
14.58 MW
Whitwell Energy Park, Southfield Lane, Whitwell, Derbyshire, S80 3LH (6 components)
• 1 x 2MW gas gen sets at Whitwell Energy Park.
• Gas reciprocating engines as the generating unit.
Active • 2027-28 (T-4), 2020-21 (T-4) ...
Waun-y-Pound Industrial Estate, Ebbw Vale, Gwent, NP23 6PL (11 components)
• 16MW power plant comprising of reciprocating engines. The power plant is connected to the local distribution network and local gas network.
• Peak power plant
Active • 2028-29 (T-4), 2027-28 (T-4) ...
14.58 MW
Watson Street Power Station, Burtonhead Road, St Helens, WA9 5EA (16 components)
• The CMU will be formed of multiple individual gas generating units controlled centrally and exporting to the distribution system.
• The CMU will be formed of multiple individual generating units controlled centrally and exporting to the distribution system.
Active • 2027-28 (T-4), 2026-27 (T-4) ...
7.27 MW
Villa Nursery, Reeves Lane, Roydon, Harlow, Essex, CM19 5LE (18 components)
• A generating station consisting on multiple reciprocating engines and alternators located on a single site
• CMU consisting of multiple reciprocating engines and alternators
Active • 2028-29 (T-4), 2027-28 (T-4) ...
2.71 MW
Unit 7, Cambridgeshire Business Park, Angel Drove, Ely CB7 4DT (5 components)

CMU consisting of multiple reciprocating engines and alternators

Active • 2027-28 (T-4), 2026-27 (T-4) ...
4.78 MW
Unit 28,29,30, Peel Mills Industrial Estate, Chamberhall Street, Bury, BL9 0LU (14 components)

16MW power plant comprising of reciprocating engines. The power plant is connected to the local distribution network and local gas network. (3)

Active • 2028-29 (T-4), 2027-28 (T-4) ...
208.85 MW
Unit 2, 105 Abercorn Street, Paisley, PA3 4AT (14 components)
• New build gas generator
• Operational reciprocating gas engines
Active • 2028-29 (T-4), 2027-28 (T-4) ...
3.74 MW
Traston Road, Off Corporation Road, Newport , Gwent, NP19 4RQ (21 components)
• The CMU will be formed of multiple individual gas generating units controlled centrally and exporting to the distribution system.
• The CMU will be formed of multiple individual generating units controlled centrally and exporting to the distribution system.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
9.35 MW
Titanium Road, Waunarlwydd, Swansea, SA5 4NH (2 components)
• New build site with gas reciprocating engines to replace diesel plant
• New gas reciprocating engines to be installed and/or existing plant to be refurbished/replaced to operate on green bio-fuel.
Active • 2028-29 (T-4), 2027-28 (T-4)
18.70 MW
3.62 MW
Thistlebrook Farm, Tring Road, Wingrave, HP22 4LN (1 component)

A New Build Distributed Connected Gas Fueled Generating Station.

Active • 2027-28 (T-4)
47.08 MW
The Canalside, Marsh Lane, off Showground Road, Bridgwater, Somerset, TA6 6LQ (17 components)
• The CMU will be formed of multiple individual gas generating units controlled centrally and exporting to the distribution system.
• The CMU will be formed of multiple individual generating units controlled centrally and exporting to the distribution system.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
9.35 MW
Tees Valley Nursery, The Moat, Belasis Hall, TS23 4ED (26 components)
• The CMU component TEES01 is one gas-fired Jenbacher CHP engine. It will be supplying heat, CO2 and power to the on-site tomato Nursery all year.
• The CMU component TEES02 is one gas-fired Jenbacher CHP engine. It will be supplying heat, CO2 and power to the on-site tomato Nursery all year.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
6.17 MW
Sutton Manor Grid Capacity Site, Union Bank Farm, Warrington Road, Bold Bridge, St Helens, WA8 5UT (8 components)

3.000MW of installed capacity of gas fuelled reciprocating engines to be installed on designated land within a manufacturing compound.

Active • 2028-29 (T-4), 2027-28 (T-4) ...
2.81 MW
Stone Circle, Shap, Cumbria, CA10 3PZ (2 components)
• A new build gas fuelled generation station
• A new build, gas fuelled generation station
Active • 2027-28 (T-4)
42.46 MW
St Asaph Power, Glascoed Road, St Asaph, Denbighshire LL17 0LQ (13 components)
• 16MW Power plant comprising reciprocating engines. The Power plant is connected to the local distribution and gas network. (2)
• 16 MW power plant comprising of reciprocating engines.The Power plant is connected to the local distribution and gas network.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
14.77 MW
Speke Hall Avenue, Speke, Liverpool, L24 8DA (3 components)
• A new build, battery energy storage system (2)
• A new build, gas fueled generation station.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
24.56 MW
South Cornelly Trading Estate, Porthcawl Road, Bridgend, CF33 4RE (18 components)

The CMU will be formed of multiple individual gas generating units controlled centrally and exporting to the distribution system. (3)

Active • 2028-29 (T-4), 2027-28 (T-4) ...
128.68 MW
Severn Road, Almondsbury, Bristol, BS10 7GD (3 components)
• A new build, gas fuelled generation station
• A new build, gas fuelled generation station.
Active • 2027-28 (T-4), 2026-27 (T-4)
4.25 MW
Loading map...
Showing 25 locations