Reciprocating engines

19 unique locations (265 components)

Recycling Centre Meek Street Rochdale OL2 6HL (2 components)

New Build Generating CMU comprising of gas fuelled reciprocating engines and gas delivery plant

Inactive • 2022-23 (T-4)
No.1 Maxwell Road Woodston Industrial Estate Peterborough PE2 7JB (8 components)
• A power plant, with associated civil works, switchgear and electrical connection.
• A recently completed power plant, with associated civil works, switchgear and electrical connection.
Active • 2027-28 (T-4), 2026-27 (T-4) ...
No.1 Maxwell Road Woodston Industrial Estate Peterborough PE2 7JB (2 components)

A recently completed power plant, with associated civil works, switchgear and electrical connection.

Inactive • 2023-24 (T-1), 2017-18 (T-1)
Millfield Lane Haydock Industrial Estate Haydock St Helens WA11 9UT (13 components)

A completed power plant, with associated civil works, switchgear and electrical connection.

Active • 2028-29 (T-4), 2027-28 (T-4) ...
25.80 MW
Millfield Lane Haydock Industrial Estate Haydock St Helens WA11 9UT (5 components)

A completed power plant, with associated civil works, switchgear and electrical connection.

Active • 2028-29 (T-4), 2026-27 (T-4) ...
15.55 MW
Land on west side of Droppingwell Road, Sheffield, S61 2DW (4 components)

3 x 2MW gas generator units to be installed on a compound adjacent to Droppingwell Road

Inactive • 2023-24 (T-4), 2022-23 (T-3)
LAND LYING TO THE SOUTH OF WEST QUAY ROAD WINWICK WA2 8TL (5 components)

CMU consisting of multiple reciprocating engines and alternators

Inactive • 2023-24 (T-4), 2022-23 (T-3) ...
Carrington Power Station 132 Manchester Road Carrington Manchester M31 4AY United Kingdom (40 components)
• The CMU component is a combined cycle gas turbine
• This CMU (CARRI3) will be formed of multiple gas reciprocating units controlled centrally & exporting to the Distribution system.
• This CMU (CGTN_3) will be formed of multiple gas reciprocating units controlled centrally & exporting to the Distribution system.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
637.73 MW
Booker Cash and Carry Frobisher Way Hatfield Hertfordshire AL10 9TR (12 components)

A completed power plant, with associated civil works, switchgear and electrical connection.

Active • 2028-29 (T-4), 2027-28 (T-4) ...
18.67 MW
Booker Cash and Carry Frobisher Way Hatfield Hertfordshire AL10 9TR (4 components)

A completed power plant, with associated civil works, switchgear and electrical connection.

Active • 2028-29 (T-4), 2023-24 (T-1) ...
9.48 MW
Booker Cash and Carry Didcot OX11 7HJ (7 components)

A completed power plant, with associated civil works, switchgear and electrical connection.

Active • 2026-27 (T-4), 2025-26 (T-4) ...
3.14 MW
Booker Cash and Carry Didcot OX11 7HJ (3 components)

A completed power plant, with associated civil works, switchgear and electrical connection.

Inactive • 2023-24 (T-1), 2022-23 (T-1) ...
3.14 MW
Batleys Cash and Carry Talbot Road Fareham PO15 5RY (11 components)
• A completed power plant, with associated civil works, switchgear and electrical connection.
• The CMU component is net of the auxiliary power required
Active • 2028-29 (T-4), 2027-28 (T-4) ...
52.31 MW
Batleys Cash and Carry Talbot Road Fareham PO15 5RY (4 components)
• A completed power plant, with associated civil works, switchgear and electrical connection.
• The CMU component is net of the auxiliary power required
Active • 2028-29 (T-4), 2023-24 (T-1) ...
33.68 MW
Batleys Cash and Carry Gielgud Way Coventry CV2 2SZ (11 components)

A completed power plant, with associated civil works, switchgear and electrical connection.

Active • 2028-29 (T-4), 2027-28 (T-4) ...
22.63 MW
Batleys Cash and Carry Gielgud Way Coventry CV2 2SZ (4 components)

A completed power plant, with associated civil works, switchgear and electrical connection.

Active • 2028-29 (T-4), 2023-24 (T-1) ...
11.32 MW
AL1 (123 components)
• Domestic EV charge point
• Domestic EV charger
• Domestic demand turn down
Active • 2027-28 (T-4), 2025-26 (T-4) ...
174.09 MW
1 Maxwell Road, Woodston Industrial Estate, Peterborough PE2 7JB (5 components)
• This CMU is 10*2MW reciprocating engines using HVO.
• This CMU is 10*2MW reciprocating engines.
• This CMU is 6*2MW reciprocating engines.
Active • 2027-28 (T-4), 2026-27 (T-4) ...
18.70 MW
1 Maxwell Road, Woodston Industrial Estate, Peterborough PE2 7JB (2 components)
• This CMU is 10*2MW reciprocating engines.
• This CMU is 6*2MW reciprocating engines.
Active • 2025-26 (T-1), 2023-24 (T-1)
18.70 MW
Loading map...
Showing 19 locations