Home Grok GrokAsk Grok (Beta) Technologies Companies Locations Map Explorer FAQ Help Login Register
Theme
Light Dark Auto
Quick Menu
Loading...
Loading...

Storage (Duration 1h)

334 unique locations (1426 components) - Page 7 of 14

Active MW: 20052.96 MW
Inactive MW: 1148.27 MW
LAND ON THE SOUTH SIDE OF FAIRY LANE, SALE, M33 2JU. (Nearest postcode to grid reference: M33 2JT). (5 components) Geocoding Needed

Battery Storage Plant

Storage Storage (Duration 1h) Storage (Duration 2h) WEST DIDSBURY STORAGE LIMITED New Build Generating CMU West Didsbury Storage West Didsbury Storage 017 +1 more M33
Active • 2024-25 (T-4), 2023-24 (T-4) ...
68.56 MW
LAND ON THE SOUTH SIDE OF FAIRY LANE, SALE, M33 2JU. (6 components) Geocoding Needed

Battery Storage Plant

Storage (Duration 1h) Storage (Duration 2h) WEST DIDSBURY STORAGE LIMITED New Build Generating CMU West Didsbury Storage West Didsbury Storage +3 more M33
Active • 2025-26 (T-4), 2024-25 (T-1) ...
37.01 MW
Land on the south east side of Lark's Lane, Latteridge, Iron Acton, BS37 9TX (2 components) Geocoding Needed

The CMU component at the Iron Acton Battery Storage Facility will be an energy storage system comprised of batteries and will have import and export capacity of 49.9MW each.

Storage Storage (Duration 1h) SOUTH WEST GRID STORAGE TWO LTD New Build Generating CMU Iron Acton Battery Storage Facility Iron Acton Battery Storage Facility Conditional BS37
Inactive • 2022-23 (T-4), 2021-22 (T-4)
23.60 MW
LAND ON THE NORTH SIDE OF DESFORD ROAD, ENDERBY, LEICESTER, LE19 3LR (11 components) Geocoding Needed

Battery Storage Plant

Storage Storage (Duration 1h) Storage (Duration 2h) Storage (Duration 4h) ENDERBY STORAGE LIMITED New Build Generating CMU Enderby Storage 019 Enderby Storage 042 +6 more LE19
Active • 2025-26 (T-4), 2024-25 (T-4) ...
144.62 MW
Land on Dalmarnock Road Trading Estate, Rutherglen, G73 1AN., See map uploaded. (4 components) Geocoding Needed

The facility consists of a lithium Ion battery storage system capable of importing, storing and exporting electricity. It connects to SPEN?s 33kV distribution network at 33kV.

Inactive • 2023-24 (T-4), 2022-23 (T-3) ...
12.11 MW
Land off Tower House Lane, Saltend, Hull, UK, HU12 8EE (2 components) Geocoding Needed

The CMU component at the Saltend Battery Storage Facility will be an energy storage system comprised of batteries and will have import and export capacity of 20.000MW each.

Storage Storage (Duration 1h) NORTH EAST GRID STORAGE ONE LTD New Build Generating CMU Saltend Battery Storage Facility Saltend Battery Storage Facility Conditional HU12
Inactive • 2022-23 (T-4), 2021-22 (T-4)
13.17 MW
Land off Sundridge Hill, Cuxton, Rochester, ME2 1LB. (9 components) Geocoding Needed
• The CMU component at Cuxton is an energy storage system comprised of batteries with an import and export capacity of 49.5MVA.
• The CMU component at Cuxton is an energy storage system comprised of batteries with an import and export capacity of 49.5MW.
• The CMU component at Cuxton is an energy storage system comprised of batteries with an import and export capacity of 49.5MW. Battery capacity will be reduced to 38.5MWh after 15 years of operation.
Storage Storage (Duration 1h) CUXTON ENERGY STORAGE LIMITED New Build Generating CMU CUX001 Cuxton Battery Storage Facility +2 more ME2
Active • 2026-27 (T-4), 2025-26 (T-4) ...
66.24 MW
Land off Stoke Lane, Norwich, NR14 8QD (3 components) Geocoding Needed
• Grid-scale energy storage system based on Lithium Ion technology, capable of exporting the declared capacity for the stated duration.
• Grid-scale energy storage system based on Lithium Ion, capable of exporting 50MW for a 1 hour duration installed on designated land within a compound at Wood Farm
Storage (Duration 1h) Storage (Duration 2h) FPC ELECTRIC LAND LIMITED New Build Generating CMU Norwich A Norwich B +1 more Not Prequalified NR14
Active • 2027-28 (T-4), 2025-26 (T-4)
30.73 MW
Land off, Old School, Lane Hereford, HR4 9BP (3 components) Geocoding Needed
• A 13MW New Build Battery Storage site
• A 6MW New Build CHP site
• A New Build Battery Storage site
Storage (Duration 1h) Combined Heat and Power (CHP) NORIKER PERSEVERANCE LTD New Build Generating CMU Perseverance Battery 1 Perseverance Battery 2 +1 more HR4
Active • 2026-27 (T-4), 2024-25 (T-4)
10.35 MW
land off Lower Farm, Itchington, South Glos. BS35 3TH. (1 component) Geocoding Needed

A 49.400 MW / 49.400 MWh battery energy storage system located in land off Lower Farm, Itchington, South Glos. BS35 3TH.

Storage (Duration 1h) IRON ACTON GREEN LIMITED New Build Generating CMU LARKS GREEN BS35
Active • 2025-26 (T-4)
9.86 MW
Land off Dunsinane Avenue, Dunsinmore Industrial Estate, Dundee, Scotland, DD2 3QF (3 components) Geocoding Needed
• 49.9MW Lithium-ion Energy Storage System
• 49MW Lithium-ion Energy Storage System
Storage (Duration 1h) SUSI EELPOWER DUNSINANE LIMITED New Build Generating CMU LYND21 LYND21 DD2
Active • 2024-25 (T-4), 2023-24 (T-1) ...
34.09 MW
Land off Carseview Road, Forfar, DD8 3BS (7 components) Geocoding Needed
• 3 gas reciprocating engines used for power generation, with associated infrastructure.
• Battery storage and associated infrastructure
Inactive • 2023-24 (T-4), 2022-23 (T-4) ...
20.96 MW
Land Off 9 Coal Pit Lane, Atherton, Manchester, M46 0RL (5 components) Geocoding Needed
• Grid-scale energy storage system based on Lithium Ion, capable of exporting 30MW for a 1 hour duration installed on designated land within a compound at Atherton
• Grid-scale energy storage system based on Lithium Ion, capable of exporting the declared capacity for a duration of 2 hours
• New Build 2.5 hour battery storage system.
Active • 2026-27 (T-4), 2025-26 (T-4) ...
28.28 MW
Land North West Of Electricity Sub-Station Weirs Drove Burwell CB25 0BP (1 component) Geocoding Needed

30MW/30MWh one hour battery storage asset located near BURWB1 asset

Active • 2026-27 (T-4)
3.54 MW
Land north of Radstock Road, Midsomer Enterprise Park, Radstock Road, Midsomer Norton, Radstock, BA3 2AF (5 components) Geocoding Needed
• Existing CMU comprising of battery storage and associated plant
• New Build CMU comprising of battery storage and associated plant
Storage (Duration 1h) Storage (Duration 2h) CONRAD (MIDSOMER) LIMITED CONRAD ENERGY (DEVELOPMENTS) LIMITED New Build Generating CMU Midsomer Norton Midsomer Norton +3 more BA3
Active • 2026-27 (T-4), 2025-26 (T-4) ...
6.46 MW
Land North of Oxford Road, Gerrards Cross, SL9 8DT (2 components) Geocoding Needed

20MW of Lithium Ion batteries and power conversion system installed on a compound on land north Oxford Road

Storage (Duration 1h) PINSTONE ENERGY CENTRE LIMITED New Build Generating CMU Not Prequalified SL9
Inactive • 2023-24 (T-4), 2022-23 (T-3)
4.18 MW
Land North of Heatherywood Road, Kirkcaldy, Fife, KY1 3NW (5 components) Geocoding Needed

New build storage facility

Storage Storage (Duration 1h) BOLSHAN RENEWABLES LIMITED New Build Generating CMU South Redhouse South Redhouse +1 more KY1
Active • 2024-25 (T-4), 2023-24 (T-4) ...
9.55 MW
Land North of Clayhill Farm, Westoning, MK45 5JD (11 components) Geocoding Needed
• 6 MW Battery Storage facility located at Westoning.
• 6.000MW of battery storage located at Westoning.
• 6.000MW of storage located at Westoning
DSR Storage Storage (Duration 1h) CLAYHILL SOLAR LIMITED Existing Generating CMU Clayhill MK45
Active • 2027-28 (T-4), 2026-27 (T-4) ...
14.24 MW
Land North of Clayhill Farm, Westoning MK45 5JD (5 components) Geocoding Needed
• 1.200MW of storage located at Land North of Clayhill Farm, Westoning MK45 5JD
• Battery storage located at Land North of Clayhill Farm, Westoning MK45 5JD with a nameplate capacity of 1.200 MW. Connection capacity is calculated as the Average Output of the Existing Generating CMU over 3 settlement periods identified over the previous months, per Capacity Market rules 3.5.3 & 3.5.4.
Storage (Duration 1h) GSES 1 LIMITED Existing Generating CMU AGABS4 Ancala (2B) +1 more MK45
Active • 2028-29 (T-4), 2027-28 (T-4) ...
1.23 MW
Land North Of Actrees Solar Farm Heathfield Alkington Gloucestershire GL13 9PP (2 components) Geocoding Needed

new build battery storage asset 49.900MW/49.900MWh one hour duration

Active • 2025-26 (T-4), 2024-25 (T-1)
9.56 MW
Land North East Of Newton Wood Farm Newtonwood Lane Newton, NEAREST DE55 5SG (4 components) Geocoding Needed

New build battery storage 50.000MW/50.000MWh one hour duration asset

Active • 2025-26 (T-4), 2024-25 (T-1) ...
22.06 MW
Land North East of Eastfield Farm, Hutton Cranswick, East Riding of Yorkshire YO25 9RB (address in planning application), Scurf Dyke Farm, Cranswick, YO25 9RD (address of grid connection point) (5 components) Geocoding Needed
• The CMU is a 52MW/52MWh Lithium Iron Battery Electric Storage System. The BESS is co-located with a solar PV plant, and shares a grid connection, but is separately metered. The solar and the BESS will be registered as separate BMUs. The Electricity Storage Facility will connect to the grid via the 132/33 kV substation of the Facility, connecting to additional panels on the 33 kV switchgear. The main assets, elements and systems forming the Electricity Storage Facility are: 26 containers with Lithium Ion battery modules (LFP), containers are furthermore including HVAC, fire extinguishing system and controls; 13 PCS skids, each comprising of 2x 2000 kVA converter, a 4 MVA 0.8/33 kV step up transformer and a 630A 33 kV Ring Main Unit (RMU)
• The CMU is a 8MW/16MWh Lithium-Ion Battery Electric Storage System. The BESS is co-located with a solar PV plant, and shares a grid connection, but is separately metered. The solar and the BESS will be registered as separate BMUs. The Electricity Storage Facility will connect to the grid via the 132/33 kV substation of the Facility, connecting to additional panels on the 33 kV switchgear. The main assets, elements and systems forming the Electricity Storage Facility are: 8 containers with Lithium Ion battery modules (LFP), containers are furthermore including HVAC, fire extinguishing system and controls; 2 PCS skids, each comprising of 2x 2000 kVA converter, a 4 MVA 0.8/33 kV step up transformer and a 630A 36 kV Ring Main Unit (RMU)
• The CMU is a 8MW/16MWh Lithium-Ion Battery Electric Storage System. The BESS is co-located with a solar PV plant, and shares a grid connection, but is separately metered. The solar and the BESS will be registered as separate BMUs. The Electricity Storage Facility will connect to the grid via the 132/33 kV substation of the Facility, connecting to additional panels on the 33 kV switchgear. The main assets, elements and systems forming the Electricity Storage Facility are: 8 containers with Lithium Ion battery modules (LFP), containers are furthermore including HVAC, fire extinguishing system and controls; 2 PCS skids, each comprising of 2x 2000 kVA converter, a 4 MVA 0.8/33 kV step up transformer and a 630A 36 kV Ring Main Unit (RMU)
Active • 2027-28 (T-4), 2026-27 (T-4) ...
18.71 MW
Land North East of Eastfield Farm, Hutton Cranswick, East Riding of Yorkshire YO25 9RB (address in planning application) Scurf Dyke Farm, Cranswick, YO25 9RD (address of grid connection point) (3 components)
• The CMU is a 8MW/16MWh Lithium-Ion Battery Electric Storage System. The BESS is co-located with a solar PV plant, and shares a grid connection, but is separately metered. The solar and the BESS will be registered as separate BMUs. The Electricity Storage Facility will connect to the grid via the 132/33 kV substation of the Facility, connecting to additional panels on the 33 kV switchgear. The main assets, elements and systems forming the Electricity Storage Facility are: 8 containers with Lithium Ion battery modules (LFP), containers are furthermore including HVAC, fire extinguishing system and controls; 2 PCS skids, each comprising of 2x 2000 kVA converter, a 4 MVA 0.8/33 kV step up transformer and a 630A 36 kV Ring Main Unit (RMU) (2)
• The CMU is a 52MW/52MWh Lithium Iron Battery Electric Storage System. The BESS is co-located with a solar PV plant, and shares a grid connection, but is separately metered. The solar and the BESS will be registered as separate BMUs. The Electricity Storage Facility will connect to the grid via the 132/33 kV substation of the Facility, connecting to additional panels on the 33 kV switchgear. The main assets, elements and systems forming the Electricity Storage Facility are: 26 containers with Lithium Ion battery modules (LFP), containers are furthermore including HVAC, fire extinguishing system and controls; 13 PCS skids, each comprising of 2x 2000 kVA converter, a 4 MVA 0.8/33 kV step up transformer and a 630A 33 kV Ring Main Unit (RMU)
Storage (Duration 1h) Storage (Duration 2h) FP LUX SCURF DYKE SOLAR LIMITED New Build Generating CMU Scurf Dyke Solar Limited Scurf Dyke Solar Limited YO25
Active • 2025-26 (T-1), 2024-25 (T-1) ...
12.03 MW
Land next to Capenhurst substation, Ledsham, Ellesmere Port, CH66 2HD (1 component) Geocoding Needed

49.9MW Battery Storage facility located at Capenhurst GSP

Storage (Duration 1h) Zenobe Capenhurst Limited New Build Generating CMU Capenhurst CH66
Active • 2024-25 (T-4)
12.36 MW
Land in the vicinity of Feeder Road, to the east of Phillip Street, Bristol BS2 0TB, UK (1 component) Geocoding Needed

The CMU component at the Feeder Road Battery Storage Facility will be an energy storage system comprised of batteries and will have import and export capacity of 20.000MW each.

Storage (Duration 1h) Aura Power Storage Solutions Ltd New Build Generating CMU Feeder Road Battery Storage Facility Conditional BS2
Inactive • 2022-23 (T-4)
5.88 MW
Loading map...