Home Technologies Companies Locations Map Explorer FAQ ChatGPTChatGPT Buy Me A Coffee Help Login Register
Theme
Light Dark Auto
Quick Menu
Loading...
Loading...

Storage (Duration 2h)

8 unique locations (100 components)

WHITLEY GOLF COURSE CORSHAM ROAD, SHAW, MELKSHAM SN12 8EQ. (Nearest postcode to grid reference: SN12 8EH). (18 components)
• Battery Storage Plant
• Battery storage unit
• Steam Driven Turbo Alternator 8G1 6,8 MWe
Active • 2024-25 (T-4), 2023-24 (T-4) ...
West Marsh Road Spalding Lincolnshire PE11 3BB (16 components)
• Battery storage located at Drayton Manor Farm, Alcester Road, Stratford-Upon-Avon, CV37 9RG with a nameplate capacity of 1.000 MW. Connection capacity is calculated as the Average Output of the Existing Generating CMU over 3 settlement periods identified over the previous months, per Capacity Market rules 3.5.3 & 3.5.4.
• Kiln Power is a 16 MW power plant comprising gas reciprocating engines. The export of the power plant is connected to the local distribution network via two separately metered 8MW connections (of which this is one of the two CMU components) and it is connected to the local gas network. Kiln Power has a single Balancing Service ID - NGSTORKILN218. To distinguish between the two components of the CMU a numbering system has been used. The two components are separately metered.
• Wind Turbines to be installed at Crossdykes Wind Farm
Active • 2027-28 (T-4), 2024-25 (T-4) ...
255.05 MW
Rosper Road Immingham North Lincolnshire DN40 3DZ (10 components)
• Battery storage unit
• Gas CHP on South bank of river Humber providing electricity and industrial steam
• New build gas reciprocating multi-engine generating plant
Active • 2028-29 (T-4), 2024-25 (T-1) ...
1165.32 MW
Lubenham Road, Market Harborough, Leicestershire, LE16 9NP *Post code and grid reference may not match because site address is not yet registered with post office. We have used nearest available post code. (5 components)
• Array of lithium ion batteries in a power generation environment, proving power to National Grid. Change of use of land from agricultural to new build generation.
• New reciprocating gensets in acoustic enclosure
• The CMU Component reduces import demand by turning off equipment and other non-essential loads.
Inactive • 2023-24 (T-4), 2022-23 (T-4) ...
Land to the west (see map) of 18-20 Netherdale Rd, Netherton Industrial Estate, Wishaw ML2 0ER (9 components)
• A new build 30MW battery energy storage system
• Load reduction on site supported by non-exporting standby generation.
• The facility consists of a series of gas fired generators. It connects to SPEN?s 33kV distribution network at 33kV
Active • 2024-25 (T-4), 2023-24 (T-4) ...
Land off Mansfield Road, Little Morton Farm, Little Morton, Retford, DN22 8HE (17 components)
• A gas fuelled electrical power generating unit comprising multiple reciprocating engines.
• Battery energy storage unit
• This CMU component is an open cycle gas turbine unit fuelled by distillate with BMU identifier T_DRAXX-12G under the BSC
Active • 2028-29 (T-4), 2027-28 (T-4) ...
14.20 MW
Land at Capenhurst Sub Station, Capenhurst, Cheshire, CH66 2HJ (6 components)
• A New Build Battery Energy Storage System
• A New Build Gas fuelled power plant at Capenhurst substation
• District heating implementation with one asset 1MW and no auxiliary load
Active • 2024-25 (T-1), 2023-24 (T-4) ...
12.92 MW
1, THE OLD BARN PURLIEUS, MINETY, MALMESBURY SN16 9RP (Nearest postcode to grid reference: SN16 9DX). (19 components)
• Battery Storage Plant
• Load reduction on site supported by non-exporting standby generation.
• Reciprocating genset in acoustic enclosure
Active • 2025-26 (T-4), 2023-24 (T-4) ...
53.56 MW
Loading map...
Showing 8 locations