Home Technologies Companies Locations Map Explorer FAQ ChatGPTChatGPT Help Login Register
Theme
Light Dark Auto
Quick Menu
Loading...
Loading...

Storage (Duration 9h)

2 unique locations (32 components)

Foyers Power Station, Foyers, Inverness, IV2 6YB (18 components)
β€’ Generating Unit 1
β€’ Generating Unit 2
Active β€’ 2024-25 (T-4), 2025-26 (T-4) ...
603.34 MW
Cowley Substation Blackberry Lane Garsington Oxfordshire OX44 9BD (14 components)
β€’ The CMU is a electro-chemical Lithium-ion battery storage system connected to the transmission system at the National Grid Transmission Substation.
β€’ The CMU is a electro-chemical battery storage system connected to the transmission system at the National Grid Transmission Substation.
Active β€’ 2024-25 (T-4), 2025-26 (T-4) ...
34.61 MW
Loading map...
Showing 2 locations