Luton Road, Chalton, Fancott, Toddington, Central Bedfordshire, England, LU5 6HT

Battery Storage Plant

SUNDON STORAGE LIMITED CMU: SEL151 Storage (Duration 5h) CMU De-Rated N/A CMU DB: 104.68 MW 2028-29 (T-4) Four Year Ahead Capacity Auction
Land south east of Sundon Substation Water End Lane Chalton, Luton LU4 9UB

The CMU is a electro-chemical battery storage system connected to the transmission system at the National Grid Transmission Substation.

Waterswallows Energy Limited CMU: WATERS Storage (Duration 2h) CMU De-Rated N/A CMU DB: 7.80 MW 2026-27 (T-4) Four Year Ahead Capacity Auction
East to Sundon NG Substation Chalton Luton LU4 9UQ

30.000 MW standalone battery energy storage project

SUNDON BATTERY STORAGE LIMITED CMU: SUND26 Storage (Duration 1h) CMU De-Rated N/A CMU DB: 3.54 MW 2026-27 (T-4) Four Year Ahead Capacity Auction
LAND EAST OF TEBWORTH, LEIGHTON BUZZARD, CENTRAL BEDFORDSHIRE, LU7 9QD.

Lithium-based battery energy storage system

SUNDON GREEN LIMITED CMU: SUNDON Storage (Duration 1.5h) CMU De-Rated N/A CMU DB: 7.09 MW 2026-27 (T-4) Four Year Ahead Capacity Auction
Land south east of Sundon Substation Water End Lane Chalton, Luton LU4 9UB

The CMU is a electro-chemical battery storage system connected to the transmission system at the National Grid Transmission Substation.

Waterswallows Energy Limited CMU: WATERS Storage (Duration 2h) CMU De-Rated N/A 2025-26 (T-4) Four Year Ahead Capacity Auction
Land south east of Sundon Substation Water End Lane Chalton, Luton LU4 9UB

The CMU is a electro-chemical battery storage system connected to the transmission system at the National Grid Transmission Substation.

Waterswallows Energy Limited CMU: WATERS Storage (Duration 2h) CMU De-Rated N/A CMU DB: 12.48 MW 2025-26 (T-1) One Year Ahead Capacity Auction
LAND EAST OF TEBWORTH, LEIGHTON BUZZARD, CENTRAL BEDFORDSHIRE, LU7 9QD.

Lithium-based battery energy storage system

SUNDON GREEN LIMITED CMU: SUNDO1 Storage (Duration 2h) CMU De-Rated N/A CMU DB: 10.83 MW 2025-26 (T-1) One Year Ahead Capacity Auction
 Luton Road, Fancott, Toddington LU5 6HT

New Build Generating CMU comprising of gas fuelled reciprocating engines and gas delivery plant.

CONRAD (SUNDON) LIMITED CMU: CDSUN5 Reciprocating engines CMU De-Rated N/A 2025-26 (T-4) Four Year Ahead Capacity Auction
Land south east of Sundon Substation Water End Lane Chalton, Luton LU4 9UB

The CMU is a electro-chemical battery storage system connected to the transmission system at the National Grid Transmission Substation.

Waterswallows Energy Limited CMU: WATERS Storage (Duration 2h) CMU De-Rated N/A 2024-25 (T-1) One Year Ahead Capacity Auction
 Luton Road, Fancott, Toddington LU5 6HT

New Build Generating CMU comprising of gas fuelled reciprocating engines and gas delivery plant

CONRAD (SUNDON) LIMITED CMU: CDSUN3 Reciprocating engines CMU De-Rated N/A 2024-25 (T-4) Four Year Ahead Capacity Auction
LAND EAST OF TEBWORTH, LEIGHTON BUZZARD, CENTRAL BEDFORDSHIRE, LU7 9QD.

Lithium-based battery energy storage system

SUNDON GREEN LIMITED CMU: SUNDO1 Storage (Duration 2h) CMU De-Rated N/A 2024-25 (T-1) One Year Ahead Capacity Auction
 Luton Road, Fancott, Toddington LU5 6HT

Existing Generating CMU comprising of gas fuelled reciprocating engines and gas delivery plant

CONRAD (SUNDON) LIMITED CMU: CDSUN4 Reciprocating engines CMU De-Rated N/A 2023-24 (T-1) One Year Ahead Capacity Auction
 Luton Road, Fancott, Toddington LU5 6HT

New Build Generating CMU comprising of gas fuelled reciprocating engines and gas delivery plant

CONRAD (SUNDON) LIMITED CMU: CDSUN4 Reciprocating engines CMU De-Rated N/A 2022-23 (T-1) One Year Ahead Capacity Auction
 Luton Road, Fancott, Toddington LU5 6HT

New Build Generating CMU comprising of gas fuelled reciprocating engines and gas delivery plant

CONRAD (SUNDON) LIMITED CMU: CDSUN3 Reciprocating engines CMU De-Rated N/A 2021-22 (T-1) One Year Ahead Capacity Auction