5 unique locations - 1.4MW total capacity

Brotherton Weir, Knottingley West Yorkshire WF11 8HR (3 components)
• 1.2 MW of demand reduction
• 1.200MW Battery Energy Storage System
• The CMU component at Knottingley is an energy storage system comprised of Lithium-ion batteries. The system will have a 1.2 MW export capacity and an import capacity of 1.2MW
DSR Storage Storage (Duration 1h) LIMEJUMP LTD Existing Generating CMU
Inactive • 2021-22 (T-1), 2019-20 (T-1) ...
Brotherton Weir, Knottingley West Yorkshire WF11 8HR (4 components)
• 1.200MW Battery Energy Storage System (2)
• 1.2 MW of demand reduction
DSR Storage Storage (Duration 1h) LIMEJUMP LTD Existing Generating CMU
Active • 2025-26 (T-4), 2024-25 (T-4) ...
Kirkthorpe Weir Kirkthorpe Wakefield West Yorkshire WF1 5SY (1 component)

The CMU component at Kirkthorpe is an energy storage system comprised of Lithium-ion batteries. The system will have a 1.2 MW export capacity and an import capacity of 1.2MW

Storage Limejump Virtual 3 Limited New Build Generating CMU
Inactive • 2018-19 (T-1)
Kirkthorpe Weir Kirkthorpe Wakefield West Yorkshire WF1 5SY (1 component)

The CMU component at Kirkthorpe is an energy storage system comprised of Lithium-ion batteries. The system will have a 1.2 MW export capacity and an import capacity of 1.2MW

Storage Limejump Virtual 3 Limited New Build Generating CMU
Inactive • 2021-22 (T-4)
Thrybergh Weir Kilnhurst Mexborough South Yorkshire S64 5TJ (4 components)
• 1.200MW Battery Energy Storage System (2)
• 1.200 MW of demand reduction
DSR Storage Storage (Duration 1h) LIMEJUMP LTD Existing Generating CMU