N/A

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 2.61
  • Connection Capacity (CMU Registry) 3 MW
  • Anticipated Capacity (CMU Registry) N/A

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name EDF ENERGY CUSTOMERS LIMITED
  • Parent Company (CMU Registry) N/A
  • Secondary Trading Email (CMU Registry) N/A
  • Secondary Trading Phone (CMU Registry) +442081861004

Basic Information

Basic Information
  • Location N/A
  • Description Onsite backup generators on multiple sites
  • Company EDF ENERGY CUSTOMERS LIMITED

Technical Details

Technical Details
  • Technology N/A
  • Generation Type N/A
  • Connection Type N/A
  • De-Rated Capacity N/A
  • Connection / DSR Capacity N/A
  • Type T-1

Auction Information

Auction Information
  • Auction 2017-18 (T-1) One Year Ahead Capacity Auction
  • Delivery Year 2,017
  • Status N/A
  • Clearing Price N/A

Additional Information

Additional Information
  • CMU ID EDFSR3
  • Location and Post Code N/A
  • Description of CMU Components Onsite backup generators on multiple sites
  • Generating Technology Class N/A
  • Company Name EDF ENERGY CUSTOMERS LIMITED
  • Auction Name 2017-18 (T-1) One Year Ahead Capacity Auction
  • _id 562,796
  • rank 0.06
  • Component ID ESR301
  • OS Grid Reference N/A
  • Primary Fuel of Component N/A
  • Permitted on-Site Generating Unit N/A
  • Pre-Refurbishing De-Rated Capacity N/A
  • Post-Refurbishing De-Rated Capacity N/A
  • Generating Capacity of on-site Generating Unit N/A

CMU Registry Data

CMU Registry Data
  • Auction Capacity Auction
  • Type T-1
  • Delivery Year 2,017
  • Name of Applicant EDF ENERGY CUSTOMERS LIMITED
  • CM Unit Name EDF Energy Smart Response CMU 3

Field Value
_id 562796
Type T-1
rank 0.0573088
CMU ID EDFSR3
Auction Name 2017-18 (T-1) One Year Ahead Capacity Auction
Component ID ESR301
Delivery Year 2017
De-Rated Capacity
null
OS Grid Reference
null
Location and Post Code N/A
Connection / DSR Capacity
null
Primary Fuel of Component
null
Generating Technology Class
null
Description of CMU Components Onsite backup generators on multiple sites
Permitted on-Site Generating Unit
null
Pre-Refurbishing De-Rated Capacity
null
Post-Refurbishing De-Rated Capacity
null
Generating Capacity of on-site Generating Unit
null

Field Value
_id 373
Type T-1
CMU ID EDFSR3
Auction Capacity Auction
Agent Name
null
Beta Value
null
Auction Name 2017-18 (T-1) One Year Ahead Capacity Auction
CM Unit Name EDF Energy Smart Response CMU 3
CM Unit Type Non CMRS
TEC Deferral
null
Unproven DSR
null
Delivery Year 2017
Opt Out Status Opt-In
Opt-Out Reason
null
Parent Company
null
DSR Test Method
null
Is FCM required
null
CM Unit Category Unproven DSR CMU
Storage Facility No
De-Rated Capacity 2.606
Name of Applicant EDF ENERGY CUSTOMERS LIMITED
Primary Fuel Type
null
Registered Holder EDF ENERGY CUSTOMERS LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity 3.044
DSR Bidding Capacity
null
Amount of Credit Cover (empty)
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 3
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary
null
Pre-Refurbishing CMU Status
null
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2017-EDFSR3-001
New Build Yet to Satisfy FCM
null
Planning Consents Conditions
null
Anticipated De-Rated Capacity
null
Term of the Capacity Agreement 1
Nature of the Security Interest
null
CMU confirmed entry into Auction Yes
Is Connection Agreement required
null
Pre-Refurbishment Bidding Status
null
Secondary Trading Contact - Email
null
Date for provision of deferred TEC
null
Pre-Refurbishing De-Rated Capacity
null
Date of Issue of Capacity Agreement 2017-02-15
List of Traded Capacity Obligations
null
Post-Refurbishing De-Rated Capacity
null
Auction Acquired Capacity Obligation 2.606
Date of Issue of DSR Test Certificate
null
Has Capacity Agreement been Suspended Yes - Suspended and repay Capacity Payments
Period for which the transfer applies
null
Secondary Trading Contact - Telephone '+442081861004
Capacity Agreement has been Terminated
null
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone
null
Delivery Years for which Agreement Valid 2017/2018
Connection Agreement Deferral Declaration
null
Date of Termination of Capacity Agreement
null
Latest Date SCM is expected to be achieved
null
Subject to Substantial Completion Milestone
null
Subject to a Minimum Completion Requirement
null
Earliest Date SCM is expected to be achieved
null
Is copy of Grid Connection Agreement required
null
Anticipated Pre-Refurbishing De-Rated Capacity
null
Anticipated Post-Refurbishing De-Rated Capacity
null
Legal Name of any Person with a Security Interest
null
Date for provision of deferred Connection Agreement
null
Duration of Capacity Agreement in First Bidding Round
null
Long-Stop Date for the Minimum Completion Requirement
null