Corringham, Stanford-le-Hope, Essex SS17 9LP UK Map

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 1,095.30
  • Connection Capacity (CMU Registry) 1,217 MW
  • Anticipated Capacity (CMU Registry) 1,095.30 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name GATEWAY ENERGY CENTRE LIMITED
  • Parent Company (CMU Registry) N/A
  • Secondary Trading Email (CMU Registry) N/A
  • Secondary Trading Phone (CMU Registry) +4401316246767

Basic Information

Basic Information
  • Location Corringham, Stanford-le-Hope, Essex SS17 9LP UK
  • Description A new combined cycle power station comprising the latest technology gas turbine(s), heat recovery steam generator(s), steam turbine(s) and associated balance of plant. This will be constructed on brownfield land in Stanford-Le-Hope, Essex. Metering of output is Net of auxillary load.
  • Company GATEWAY ENERGY CENTRE LIMITED

Technical Details

Technical Details
  • Technology N/A
  • Generation Type N/A
  • Connection Type N/A
  • De-Rated Capacity N/A
  • Connection / DSR Capacity N/A
  • Type T-4

Auction Information

Auction Information
  • Auction 2020-21 (T-4) Four Year Ahead Capacity Auction
  • Delivery Year 2,020
  • Status N/A
  • Clearing Price N/A

Additional Information

Additional Information
  • CMU ID IGGATE
  • Location and Post Code Corringham, Stanford-le-Hope, Essex SS17 9LP UK
  • Description of CMU Components A new combined cycle power station comprising the latest technology gas turbine(s), heat recovery steam generator(s), steam turbine(s) and associated balance of plant. This will be constructed on brownfield land in Stanford-Le-Hope, Essex. Metering of output is Net of auxillary load.
  • Generating Technology Class N/A
  • Company Name GATEWAY ENERGY CENTRE LIMITED
  • Auction Name 2020-21 (T-4) Four Year Ahead Capacity Auction
  • _id 277,787
  • rank 0.06
  • Component ID T_COSO-2
  • OS Grid Reference TQ 732 821
  • Primary Fuel of Component N/A
  • Permitted on-Site Generating Unit N/A
  • Pre-Refurbishing De-Rated Capacity N/A
  • Post-Refurbishing De-Rated Capacity N/A
  • Generating Capacity of on-site Generating Unit N/A

CMU Registry Data

CMU Registry Data
  • Auction Capacity Auction
  • Type T-4
  • Delivery Year 2,020
  • Name of Applicant GATEWAY ENERGY CENTRE LIMITED
  • CM Unit Name Gateway Energy Centre

Field Value
_id 277787
Type T-4
rank 0.0573088
CMU ID IGGATE
Auction Name 2020-21 (T-4) Four Year Ahead Capacity Auction
Component ID T_COSO-2
Delivery Year 2020
De-Rated Capacity
null
OS Grid Reference TQ 732 821
Location and Post Code Corringham, Stanford-le-Hope, Essex SS17 9LP UK
Connection / DSR Capacity
null
Primary Fuel of Component
null
Generating Technology Class
null
Description of CMU Components A new combined cycle power station comprising the latest technology gas turbine(s), heat recovery steam generator(s), steam turbine(s) and associated balance of plant. This will be constructed on brownfield land in Stanford-Le-Hope, Essex. Metering of output is Net of auxillary load.
Permitted on-Site Generating Unit
null
Pre-Refurbishing De-Rated Capacity
null
Post-Refurbishing De-Rated Capacity
null
Generating Capacity of on-site Generating Unit
null

Field Value
_id 4214
Type T-4
CMU ID IGGATE
Auction Capacity Auction
Agent Name
null
Beta Value
null
Auction Name 2020-21 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Gateway Energy Centre
CM Unit Type CMRS
TEC Deferral
null
Unproven DSR
null
Delivery Year 2020
Opt Out Status Opt-In
Opt-Out Reason
null
Parent Company
null
DSR Test Method
null
Is FCM required
null
CM Unit Category New Build Generating CMU
Storage Facility No
De-Rated Capacity 1095.3
Name of Applicant GATEWAY ENERGY CENTRE LIMITED
Primary Fuel Type
null
Registered Holder
null
Annual Penalty Cap
null
Monthly Penalty Cap
null
Proven DSR Capacity
null
DSR Bidding Capacity
null
Amount of Credit Cover (empty)
Termination Fee 1 Rate
null
Termination Fee 2 Rate
null
Termination Fee 3 Rate
null
Termination Fee 4 Rate
null
Termination Fee 5 Rate
null
Connection / DSR Capacity 1217
Maximum Obligation Period 15
Capacity Agreement Awarded No
Pre-Qualification Decision Prequalified
Capacity obligation Summary
null
Pre-Refurbishing CMU Status
null
Transmission / Distribution Transmission
Unique Agreement Identifier
null
New Build Yet to Satisfy FCM Yes
Planning Consents Conditions
null
Anticipated De-Rated Capacity 1095.3
Term of the Capacity Agreement
null
Nature of the Security Interest
null
CMU confirmed entry into Auction Yes
Is Connection Agreement required
null
Pre-Refurbishment Bidding Status
null
Secondary Trading Contact - Email
null
Date for provision of deferred TEC
null
Pre-Refurbishing De-Rated Capacity
null
Date of Issue of Capacity Agreement
null
List of Traded Capacity Obligations
null
Post-Refurbishing De-Rated Capacity
null
Auction Acquired Capacity Obligation
null
Date of Issue of DSR Test Certificate
null
Has Capacity Agreement been Suspended
null
Period for which the transfer applies
null
Secondary Trading Contact - Telephone '+4401316246767
Capacity Agreement has been Terminated
null
Duration of Capacity Agreement Awarded
null
Date for Financial Commitment Milestone
null
Delivery Years for which Agreement Valid
null
Connection Agreement Deferral Declaration
null
Date of Termination of Capacity Agreement
null
Latest Date SCM is expected to be achieved
null
Subject to Substantial Completion Milestone
null
Subject to a Minimum Completion Requirement
null
Earliest Date SCM is expected to be achieved
null
Is copy of Grid Connection Agreement required
null
Anticipated Pre-Refurbishing De-Rated Capacity
null
Anticipated Post-Refurbishing De-Rated Capacity
null
Legal Name of any Person with a Security Interest
null
Date for provision of deferred Connection Agreement
null
Duration of Capacity Agreement in First Bidding Round 15
Long-Stop Date for the Minimum Completion Requirement
null