Field | Value |
---|---|
_id | 140243 |
Type | T-4 |
rank | 0.0573088 |
CMU ID | NDAFSD |
Auction Name | 2022-23 (T-4) Four Year Ahead Capacity Auction |
Component ID | E_FELL-1 |
Delivery Year | 2022 |
De-Rated Capacity |
null |
OS Grid Reference | NY 035 035 |
Location and Post Code | Fellside CHP Sellafield Ltd Seascale Cumbria CA20 1PG UK |
Connection / DSR Capacity |
null |
Primary Fuel of Component |
null |
Generating Technology Class | Combined Heat and Power (CHP) |
Description of CMU Components | Fellside CHP is located in Seascale- Cumbria- UK and consists of three GE Frame 6581B gas turbines which are able to run on natural gas or distillate. The primary purpose of the plant is to provide critical process steam to the adjacent Sellafield nuclear reprocessing facility. The plant is embedded on the distribution network but due to its capacity also has a 132kV connection to the transmission system. The plant has a distribution connection capacity of 215MVA and a power factor of 0.85 has been used for calculation purposes. |
Permitted on-Site Generating Unit |
null |
Pre-Refurbishing De-Rated Capacity |
null |
Post-Refurbishing De-Rated Capacity |
null |
Generating Capacity of on-site Generating Unit |
null |
Field | Value |
---|---|
_id | 8506 |
Type | T-4 |
CMU ID | NDAFSD |
Auction | Capacity Auction |
Agent Name |
null |
Beta Value |
null |
Auction Name | 2022-23 (T-4) Four Year Ahead Capacity Auction |
CM Unit Name | Fellside CHP Power Station |
CM Unit Type | CMRS |
TEC Deferral |
null |
Unproven DSR |
null |
Delivery Year | 2022 |
Opt Out Status | Opt-Out |
Opt-Out Reason | Closed down, decommissioned or otherwise non-operational by the start of the relevant Delivery Year |
Parent Company |
null |
DSR Test Method |
null |
Is FCM required |
null |
CM Unit Category | Existing Generating CMU |
Storage Facility | No |
De-Rated Capacity | (empty) |
Name of Applicant | Nuclear Decommissioning Authority |
Primary Fuel Type |
null |
Registered Holder |
null |
Annual Penalty Cap |
null |
Monthly Penalty Cap |
null |
Proven DSR Capacity |
null |
DSR Bidding Capacity |
null |
Amount of Credit Cover | (empty) |
Termination Fee 1 Rate |
null |
Termination Fee 2 Rate |
null |
Termination Fee 3 Rate |
null |
Termination Fee 4 Rate |
null |
Termination Fee 5 Rate |
null |
Connection / DSR Capacity |
null |
Maximum Obligation Period |
null |
Capacity Agreement Awarded |
null |
Pre-Qualification Decision |
null |
Capacity obligation Summary |
null |
Pre-Refurbishing CMU Status |
null |
Transmission / Distribution | Distribution |
Unique Agreement Identifier |
null |
New Build Yet to Satisfy FCM |
null |
Planning Consents Conditions |
null |
Anticipated De-Rated Capacity | 97.556 |
Term of the Capacity Agreement |
null |
Nature of the Security Interest |
null |
CMU confirmed entry into Auction |
null |
Is Connection Agreement required |
null |
Pre-Refurbishment Bidding Status |
null |
Secondary Trading Contact - Email | [email protected] |
Date for provision of deferred TEC |
null |
Pre-Refurbishing De-Rated Capacity |
null |
Date of Issue of Capacity Agreement |
null |
List of Traded Capacity Obligations |
null |
Post-Refurbishing De-Rated Capacity |
null |
Auction Acquired Capacity Obligation |
null |
Date of Issue of DSR Test Certificate |
null |
Has Capacity Agreement been Suspended |
null |
Period for which the transfer applies |
null |
Secondary Trading Contact - Telephone | '+441925802409 |
Capacity Agreement has been Terminated |
null |
Duration of Capacity Agreement Awarded |
null |
Date for Financial Commitment Milestone |
null |
Delivery Years for which Agreement Valid |
null |
Connection Agreement Deferral Declaration |
null |
Date of Termination of Capacity Agreement |
null |
Latest Date SCM is expected to be achieved |
null |
Subject to Substantial Completion Milestone |
null |
Subject to a Minimum Completion Requirement |
null |
Earliest Date SCM is expected to be achieved |
null |
Is copy of Grid Connection Agreement required |
null |
Anticipated Pre-Refurbishing De-Rated Capacity |
null |
Anticipated Post-Refurbishing De-Rated Capacity |
null |
Legal Name of any Person with a Security Interest |
null |
Date for provision of deferred Connection Agreement |
null |
Duration of Capacity Agreement in First Bidding Round |
null |
Long-Stop Date for the Minimum Completion Requirement |
null |