Seabank Power Limited Severn Road, Hallen, Bristol BS10 7SP Map

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 1,149.06
  • Connection Capacity (CMU Registry) 1,258 MW
  • Anticipated Capacity (CMU Registry) 1,149.06 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name SEABANK POWER LIMITED
  • Parent Company (CMU Registry) N/A
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4401179387800

Basic Information

Basic Information
  • Location Seabank Power Limited Severn Road, Hallen, Bristol BS10 7SP
  • Description Single Shaft CCGT (Module 2)
  • Company SEABANK POWER LIMITED

Technical Details

Technical Details
  • Technology Combined Cycle Gas Turbine (CCGT)
  • Generation Type N/A
  • Connection Type N/A
  • De-Rated Capacity N/A
  • Connection / DSR Capacity N/A
  • Type T-4

Auction Information

Auction Information
  • Auction 2021-22 (T-4) Four Year Ahead Capacity Auction
  • Delivery Year 2,021
  • Status N/A
  • Clearing Price N/A

Additional Information

Additional Information
  • CMU ID SEA1_2
  • Location and Post Code Seabank Power Limited Severn Road, Hallen, Bristol BS10 7SP
  • Description of CMU Components Single Shaft CCGT (Module 2)
  • Generating Technology Class Combined Cycle Gas Turbine (CCGT)
  • Company Name SEABANK POWER LIMITED
  • Auction Name 2021-22 (T-4) Four Year Ahead Capacity Auction
  • _id 277,553
  • rank 0.09
  • Component ID T_SEAB-2
  • OS Grid Reference N/A
  • Primary Fuel of Component N/A
  • Permitted on-Site Generating Unit N/A
  • Pre-Refurbishing De-Rated Capacity N/A
  • Post-Refurbishing De-Rated Capacity N/A
  • Generating Capacity of on-site Generating Unit N/A

CMU Registry Data

CMU Registry Data
  • Auction Capacity Auction
  • Type T-4
  • Delivery Year 2,026
  • Name of Applicant SEABANK POWER LIMITED
  • CM Unit Name Seabank 1 and 2

Field Value
_id 277553
Type T-4
rank 0.09329
CMU ID SEA1_2
Auction Name 2021-22 (T-4) Four Year Ahead Capacity Auction
Component ID T_SEAB-2
Delivery Year 2021
De-Rated Capacity
null
OS Grid Reference
null
Location and Post Code Seabank Power Limited Severn Road, Hallen, Bristol BS10 7SP
Connection / DSR Capacity
null
Primary Fuel of Component
null
Generating Technology Class Combined Cycle Gas Turbine (CCGT)
Description of CMU Components Single Shaft CCGT (Module 2)
Permitted on-Site Generating Unit
null
Pre-Refurbishing De-Rated Capacity
null
Post-Refurbishing De-Rated Capacity
null
Generating Capacity of on-site Generating Unit
null

Field Value
_id 13971
Type T-4
CMU ID SEA1_2
Auction Capacity Auction
Agent Name
null
Beta Value
null
Auction Name 2026-27 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Seabank 1 and 2
CM Unit Type CMRS
TEC Deferral
null
Unproven DSR
null
Delivery Year 2026
Opt Out Status Opt-In
Opt-Out Reason
null
Parent Company
null
DSR Test Method
null
Is FCM required
null
CM Unit Category Existing Generating CMU
Storage Facility No
De-Rated Capacity 1149.057
Name of Applicant SEABANK POWER LIMITED
Primary Fuel Type Gas
Registered Holder SEABANK POWER LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity
null
DSR Bidding Capacity
null
Amount of Credit Cover (empty)
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 1258
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary
null
Pre-Refurbishing CMU Status
null
Transmission / Distribution Transmission
Unique Agreement Identifier CAN-2026-SEA1_2-001
New Build Yet to Satisfy FCM
null
Planning Consents Conditions
null
Anticipated De-Rated Capacity 1149.057
Term of the Capacity Agreement 1
Nature of the Security Interest
null
CMU confirmed entry into Auction Yes
Is Connection Agreement required
null
Pre-Refurbishment Bidding Status
null
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC
null
Pre-Refurbishing De-Rated Capacity
null
Date of Issue of Capacity Agreement 2023-03-31
List of Traded Capacity Obligations
null
Post-Refurbishing De-Rated Capacity
null
Auction Acquired Capacity Obligation 1149.057
Date of Issue of DSR Test Certificate
null
Has Capacity Agreement been Suspended
null
Period for which the transfer applies
null
Secondary Trading Contact - Telephone '+4401179387800
Capacity Agreement has been Terminated
null
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone
null
Delivery Years for which Agreement Valid 2026/2027
Connection Agreement Deferral Declaration
null
Date of Termination of Capacity Agreement
null
Latest Date SCM is expected to be achieved
null
Subject to Substantial Completion Milestone
null
Subject to a Minimum Completion Requirement
null
Earliest Date SCM is expected to be achieved
null
Is copy of Grid Connection Agreement required
null
Anticipated Pre-Refurbishing De-Rated Capacity
null
Anticipated Post-Refurbishing De-Rated Capacity
null
Legal Name of any Person with a Security Interest
null
Date for provision of deferred Connection Agreement
null
Duration of Capacity Agreement in First Bidding Round 1
Long-Stop Date for the Minimum Completion Requirement
null