Showground, Bridgewater, TA6 6PS Map

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 6.86
  • Connection Capacity (CMU Registry) 7.75 MW
  • Anticipated Capacity (CMU Registry) 6.86 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name KIWI POWER LTD
  • Parent Company (CMU Registry) General Electricity Holdings
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +447708215111

Basic Information

Basic Information
  • Location Showground, Bridgewater, TA6 6PS
  • Description Energy from waste plant
  • Company KIWI POWER LTD

Technical Details

Technical Details
  • Technology Energy from Waste
  • Generation Type N/A
  • Connection Type N/A
  • De-Rated Capacity 6.86
  • Connection / DSR Capacity 7.75
  • Type ST

Auction Information

Auction Information
  • Auction 2024-25 (T-1) One Year Ahead Capacity Auction
  • Delivery Year 2,024
  • Status N/A
  • Clearing Price N/A

Additional Information

Additional Information
  • CMU ID EEG008
  • Location and Post Code Showground, Bridgewater, TA6 6PS
  • Description of CMU Components Energy from waste plant
  • Generating Technology Class Energy from Waste
  • Company Name KIWI POWER LTD
  • Auction Name 2024-25 (T-1) One Year Ahead Capacity Auction
  • _id 469,829
  • rank 0.06
  • Component ID BRWTR1
  • OS Grid Reference ST 303 346
  • Primary Fuel of Component Waste
  • Permitted on-Site Generating Unit N/A
  • Pre-Refurbishing De-Rated Capacity N/A
  • Post-Refurbishing De-Rated Capacity N/A
  • Generating Capacity of on-site Generating Unit N/A

CMU Registry Data

CMU Registry Data
  • Auction Capacity Auction
  • Type ST
  • Delivery Year 2,024
  • Name of Applicant KIWI POWER LTD
  • CM Unit Name EEG008

Field Value
_id 469829
Type ST
rank 0.0573088
CMU ID EEG008
Auction Name 2024-25 (T-1) One Year Ahead Capacity Auction
Component ID BRWTR1
Delivery Year 2024
De-Rated Capacity 6.86
OS Grid Reference ST 303 346
Location and Post Code Showground, Bridgewater, TA6 6PS
Connection / DSR Capacity 7.75
Primary Fuel of Component Waste
Generating Technology Class Energy from Waste
Description of CMU Components Energy from waste plant
Permitted on-Site Generating Unit
null
Pre-Refurbishing De-Rated Capacity
null
Post-Refurbishing De-Rated Capacity
null
Generating Capacity of on-site Generating Unit
null

Field Value
_id 10569
Type ST
CMU ID EEG008
Auction Capacity Auction
Agent Name
null
Beta Value
null
Auction Name 2024-25 (T-1) One Year Ahead Capacity Auction
CM Unit Name EEG008
CM Unit Type Non CMRS
TEC Deferral
null
Unproven DSR
null
Delivery Year 2024
Opt Out Status Opt-In
Opt-Out Reason
null
Parent Company General Electricity Holdings
DSR Test Method
null
Is FCM required
null
CM Unit Category Existing Generating CMU
Storage Facility No
De-Rated Capacity 6.86
Name of Applicant KIWI POWER LTD
Primary Fuel Type Waste
Registered Holder KIWI POWER LTD
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity
null
DSR Bidding Capacity
null
Amount of Credit Cover
null
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 7.75
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary 01/10/2024 - 30/09/2025:6.860 MW
Pre-Refurbishing CMU Status
null
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2024-EEG008-001
New Build Yet to Satisfy FCM
null
Planning Consents Conditions
null
Anticipated De-Rated Capacity 6.86
Term of the Capacity Agreement 1
Nature of the Security Interest
null
CMU confirmed entry into Auction
null
Is Connection Agreement required
null
Pre-Refurbishment Bidding Status
null
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC
null
Pre-Refurbishing De-Rated Capacity
null
Date of Issue of Capacity Agreement 2024-09-02
List of Traded Capacity Obligations T1: 6.860 MW
Post-Refurbishing De-Rated Capacity
null
Auction Acquired Capacity Obligation (empty)
Date of Issue of DSR Test Certificate
null
Has Capacity Agreement been Suspended
null
Period for which the transfer applies T1: 01/10/2024 - 30/09/2025
Secondary Trading Contact - Telephone '+447708215111
Capacity Agreement has been Terminated
null
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone
null
Delivery Years for which Agreement Valid 2024/2025
Connection Agreement Deferral Declaration
null
Date of Termination of Capacity Agreement
null
Latest Date SCM is expected to be achieved
null
Subject to Substantial Completion Milestone
null
Subject to a Minimum Completion Requirement
null
Earliest Date SCM is expected to be achieved
null
Is copy of Grid Connection Agreement required
null
Anticipated Pre-Refurbishing De-Rated Capacity
null
Anticipated Post-Refurbishing De-Rated Capacity
null
Legal Name of any Person with a Security Interest
null
Date for provision of deferred Connection Agreement
null
Duration of Capacity Agreement in First Bidding Round
null
Long-Stop Date for the Minimum Completion Requirement
null