Search Map View Statistics Support Us Help Login Register
Saunders Way Cullompton EX15 1B Map

General Information

Key Details
  • Description Agriculture and animal feeds
  • Auction 2017-18 (TR) Transitional Capacity Auction
  • Delivery Year 2017
Geocoding Status: Yes

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 17.38
  • Connection Capacity (CMU Registry) 20 MW
  • Anticipated Capacity (CMU Registry) N/A

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name SMARTESTENERGY LIMITED
  • Parent Company (CMU Registry) N/A
  • Secondary Trading Email (CMU Registry) N/A
  • Secondary Trading Phone (CMU Registry) +4407860946003

Field Value
_id 567339
Type TR
rank 0.211562
CMU ID SEL-3c
Auction Name 2017-18 (TR) Transitional Capacity Auction
Component ID 10011
Delivery Year 2017
De-Rated Capacity (empty)
OS Grid Reference ST 030 078
Location and Post Code Saunders Way Cullompton EX15 1B
Connection / DSR Capacity (empty)
Primary Fuel of Component (empty)
Generating Technology Class (empty)
Description of CMU Components Agriculture and animal feeds
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 920
Type TR
CMU ID SEL-3c
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2017-18 (TR) Transitional Capacity Auction
CM Unit Name SmartestEnergy DSR 3
CM Unit Type Non CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2017
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company (empty)
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category Unproven DSR CMU
Storage Facility No
De-Rated Capacity 17.376
Name of Applicant SMARTESTENERGY LIMITED
Primary Fuel Type (empty)
Registered Holder SMARTESTENERGY LIMITED
Annual Penalty Cap (empty)
Monthly Penalty Cap (empty)
Proven DSR Capacity 19.808
DSR Bidding Capacity 17.376
Amount of Credit Cover (empty)
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 20
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2017-SEL-3c-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity (empty)
Term of the Capacity Agreement 1
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email (empty)
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2017-03-29
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 17.376
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+4407860946003
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2017/2018
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round (empty)
Long-Stop Date for the Minimum Completion Requirement (empty)