BOC Middlesbrough, Teessdock Road, Grangetown, TS6 7RT Map

General Information

Key Details
  • Description Industrial Gases production site. DSR provided through process interruption.
  • Auction 2017-18 (TR) Transitional Capacity Auction
  • Delivery Year 2017
Geocoding Status: Yes

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 16.37
  • Connection Capacity (CMU Registry) 20.49 MW
  • Anticipated Capacity (CMU Registry) 27.95 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name BOC LIMITED
  • Parent Company (CMU Registry) BOC Group Limited (00022096)
  • Secondary Trading Email (CMU Registry) andrew.sugden@boc.com
  • Secondary Trading Phone (CMU Registry) +4407789878173

Field Value
_id 566199
Type TR
rank 0.0573088
CMU ID TLGUK2
Auction Name 2017-18 (TR) Transitional Capacity Auction
Component ID 01MBRO
Delivery Year 2017
De-Rated Capacity
null
OS Grid Reference NZ 558 228
Location and Post Code BOC Middlesbrough, Teessdock Road, Grangetown, TS6 7RT
Connection / DSR Capacity
null
Primary Fuel of Component
null
Generating Technology Class
null
Description of CMU Components Industrial Gases production site. DSR provided through process interruption.
Permitted on-Site Generating Unit
null
Pre-Refurbishing De-Rated Capacity
null
Post-Refurbishing De-Rated Capacity
null
Generating Capacity of on-site Generating Unit
null

Field Value
_id 12285
Type T-1
CMU ID TLGUK2
Auction Capacity Auction
Agent Name
null
Beta Value
null
Auction Name 2025-26 (T-1) One Year Ahead Capacity Auction
CM Unit Name TLGUK
CM Unit Type Non CMRS
TEC Deferral
null
Unproven DSR
null
Delivery Year 2025
Opt Out Status Opt-In
Opt-Out Reason
null
Parent Company BOC Group Limited (00022096)
DSR Test Method Post Auction DSR Test
Is FCM required
null
CM Unit Category Proven DSR CMU
Storage Facility No
De-Rated Capacity 16.367
Name of Applicant BOC LIMITED
Primary Fuel Type DSR
Registered Holder BOC LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity 20.492
DSR Bidding Capacity 13
Amount of Credit Cover
null
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 20.492
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary
null
Pre-Refurbishing CMU Status
null
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2025-TLGUK2-001
New Build Yet to Satisfy FCM
null
Planning Consents Conditions
null
Anticipated De-Rated Capacity 27.955
Term of the Capacity Agreement 1
Nature of the Security Interest
null
CMU confirmed entry into Auction Yes
Is Connection Agreement required
null
Pre-Refurbishment Bidding Status
null
Secondary Trading Contact - Email andrew.sugden@boc.com
Date for provision of deferred TEC
null
Pre-Refurbishing De-Rated Capacity
null
Date of Issue of Capacity Agreement 2025-03-31
List of Traded Capacity Obligations
null
Post-Refurbishing De-Rated Capacity
null
Auction Acquired Capacity Obligation 13
Date of Issue of DSR Test Certificate 2023-08-25
Has Capacity Agreement been Suspended
null
Period for which the transfer applies
null
Secondary Trading Contact - Telephone '+4407789878173
Capacity Agreement has been Terminated
null
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone
null
Delivery Years for which Agreement Valid 2025/2026
Connection Agreement Deferral Declaration
null
Date of Termination of Capacity Agreement
null
Latest Date SCM is expected to be achieved
null
Subject to Substantial Completion Milestone
null
Subject to a Minimum Completion Requirement
null
Earliest Date SCM is expected to be achieved
null
Is copy of Grid Connection Agreement required
null
Anticipated Pre-Refurbishing De-Rated Capacity
null
Anticipated Post-Refurbishing De-Rated Capacity
null
Legal Name of any Person with a Security Interest
null
Date for provision of deferred Connection Agreement
null
Duration of Capacity Agreement in First Bidding Round 1
Long-Stop Date for the Minimum Completion Requirement
null