Old Gloucester Road, Alveston, Bristol, UK, BS35 3TD Map

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) 2.71 MW
  • De-Rated Capacity (CMU Registry) 2.71
  • Connection Capacity (CMU Registry) 10 MW
  • Anticipated Capacity (CMU Registry) 2.71 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name ECOTRICITY (SMART GRID) LIMITED
  • Parent Company (CMU Registry) ECOTRICITY GROUP LTD
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4401453790163

Basic Information

Basic Information
  • Location Old Gloucester Road, Alveston, Bristol, UK, BS35 3TD
  • Description This CMU is formed of a battery bank and PCS capable of providing 10MW of power with 23.9MWh of usable energy storage (2 hour duration). The system is connected via switch gear and a transformer to the 132kV network in NGED's South West region.
  • Company ECOTRICITY (SMART GRID) LIMITED

Technical Details

Technical Details
  • Technology Storage (Duration 2h)
  • Generation Type N/A
  • Connection Type N/A
  • De-Rated Capacity 2.71
  • Connection / DSR Capacity 10
  • Type T-1

Auction Information

Auction Information
  • Auction 2025-26 (T-1) One Year Ahead Capacity Auction
  • Delivery Year 2,025
  • Status N/A
  • Clearing Price N/A

Additional Information

Additional Information
  • CMU ID ALBESE
  • Location and Post Code Old Gloucester Road, Alveston, Bristol, UK, BS35 3TD
  • Description of CMU Components This CMU is formed of a battery bank and PCS capable of providing 10MW of power with 23.9MWh of usable energy storage (2 hour duration). The system is connected via switch gear and a transformer to the 132kV network in NGED's South West region.
  • Generating Technology Class Storage (Duration 2h)
  • Company Name ECOTRICITY (SMART GRID) LIMITED
  • Auction Name 2025-26 (T-1) One Year Ahead Capacity Auction
  • _id 530,531
  • rank 0.06
  • Component ID ALVB-1
  • OS Grid Reference ST 649 846
  • Primary Fuel of Component Storage - Battery
  • Permitted on-Site Generating Unit N/A
  • Pre-Refurbishing De-Rated Capacity N/A
  • Post-Refurbishing De-Rated Capacity N/A
  • Generating Capacity of on-site Generating Unit N/A

CMU Registry Data

CMU Registry Data
  • Auction Capacity Auction
  • Type T-1
  • Delivery Year 2,025
  • Name of Applicant ECOTRICITY (SMART GRID) LIMITED
  • CM Unit Name Alveston 10MW Battery Storage

Field Value
_id 530531
Type T-1
rank 0.0573088
CMU ID ALBESE
Auction Name 2025-26 (T-1) One Year Ahead Capacity Auction
Component ID ALVB-1
Delivery Year 2025
De-Rated Capacity 2.715
OS Grid Reference ST 649 846
Location and Post Code Old Gloucester Road, Alveston, Bristol, UK, BS35 3TD
Connection / DSR Capacity 10
Primary Fuel of Component Storage - Battery
Generating Technology Class Storage (Duration 2h)
Description of CMU Components This CMU is formed of a battery bank and PCS capable of providing 10MW of power with 23.9MWh of usable energy storage (2 hour duration). The system is connected via switch gear and a transformer to the 132kV network in NGED's South West region.
Permitted on-Site Generating Unit
null
Pre-Refurbishing De-Rated Capacity
null
Post-Refurbishing De-Rated Capacity
null
Generating Capacity of on-site Generating Unit
null

Field Value
_id 11898
Type T-1
CMU ID ALBESE
Auction Capacity Auction
Agent Name
null
Beta Value
null
Auction Name 2025-26 (T-1) One Year Ahead Capacity Auction
CM Unit Name Alveston 10MW Battery Storage
CM Unit Type Non CMRS
TEC Deferral
null
Unproven DSR
null
Delivery Year 2025
Opt Out Status Opt-In
Opt-Out Reason
null
Parent Company ECOTRICITY GROUP LTD
DSR Test Method
null
Is FCM required
null
CM Unit Category Existing Generating CMU
Storage Facility Yes
De-Rated Capacity 2.715
Name of Applicant ECOTRICITY (SMART GRID) LIMITED
Primary Fuel Type Storage - Battery
Registered Holder ECOTRICITY (SMART GRID) LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity
null
DSR Bidding Capacity
null
Amount of Credit Cover
null
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 10
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary
null
Pre-Refurbishing CMU Status
null
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2025-ALBESE-001
New Build Yet to Satisfy FCM
null
Planning Consents Conditions
null
Anticipated De-Rated Capacity 2.715
Term of the Capacity Agreement 1
Nature of the Security Interest
null
CMU confirmed entry into Auction Yes
Is Connection Agreement required
null
Pre-Refurbishment Bidding Status
null
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC
null
Pre-Refurbishing De-Rated Capacity
null
Date of Issue of Capacity Agreement 2025-03-31
List of Traded Capacity Obligations
null
Post-Refurbishing De-Rated Capacity
null
Auction Acquired Capacity Obligation 2.715
Date of Issue of DSR Test Certificate
null
Has Capacity Agreement been Suspended
null
Period for which the transfer applies
null
Secondary Trading Contact - Telephone '+4401453790163
Capacity Agreement has been Terminated
null
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone
null
Delivery Years for which Agreement Valid 2025/2026
Connection Agreement Deferral Declaration
null
Date of Termination of Capacity Agreement
null
Latest Date SCM is expected to be achieved
null
Subject to Substantial Completion Milestone
null
Subject to a Minimum Completion Requirement
null
Earliest Date SCM is expected to be achieved
null
Is copy of Grid Connection Agreement required
null
Anticipated Pre-Refurbishing De-Rated Capacity
null
Anticipated Post-Refurbishing De-Rated Capacity
null
Legal Name of any Person with a Security Interest
null
Date for provision of deferred Connection Agreement
null
Duration of Capacity Agreement in First Bidding Round 1
Long-Stop Date for the Minimum Completion Requirement
null