Old Church Lane, Mountnessing, Hutton, Brentwood, Essex, England, CM13 1UN, United Kingdom Map

General Information

Key Details
  • Description 50MW/50MWh one hour battery storage
  • Auction 2025-26 (T-1) One Year Ahead Capacity Auction
  • Delivery Year 2025
Geocoding Status: Yes

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) 6.68 MW
  • De-Rated Capacity (CMU Registry) 6.68
  • Connection Capacity (CMU Registry) 49 MW
  • Anticipated Capacity (CMU Registry) 6.68 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name CARE POWER (BRENTWOOD) LIMITED
  • Parent Company (CMU Registry) SMS Energy Services Limited
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4402920054151

Field Value
_id 534778
Type T-1
rank 0.0706241
CMU ID EBRETB
Auction Name 2025-26 (T-1) One Year Ahead Capacity Auction
Component ID EBRETB
Delivery Year 2025
De-Rated Capacity 6.684
OS Grid Reference TQ 636 961
Location and Post Code Old Church Lane, Mountnessing, Hutton, Brentwood, Essex, England, CM13 1UN, United Kingdom
Connection / DSR Capacity 49
Primary Fuel of Component Storage - Battery
Generating Technology Class Storage (Duration 1h)
Description of CMU Components 50MW/50MWh one hour battery storage
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 11989
Type T-1
CMU ID EBRETB
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2025-26 (T-1) One Year Ahead Capacity Auction
CM Unit Name EBRETB
CM Unit Type CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2025
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company SMS Energy Services Limited
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category Existing Generating CMU
Storage Facility Yes
De-Rated Capacity 6.684
Name of Applicant CARE POWER (BRENTWOOD) LIMITED
Primary Fuel Type Storage - Battery
Registered Holder CARE POWER (BRENTWOOD) LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 49
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2025-EBRETB-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 6.684
Term of the Capacity Agreement 1
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2025-03-31
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 6.684
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+4402920054151
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2025/2026
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 1
Long-Stop Date for the Minimum Completion Requirement (empty)