100 Montifichet Road, Westfield, Stratford E20 1GR Map

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) 2.81 MW
  • De-Rated Capacity (CMU Registry) 5.62
  • Connection Capacity (CMU Registry) 6.18 MW
  • Anticipated Capacity (CMU Registry) 5.31 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name EAST LONDON ENERGY LIMITED
  • Parent Company (CMU Registry) BRING ENERGY GROUP LIMITED
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4407811071199

Basic Information

Basic Information
  • Location 100 Montifichet Road, Westfield, Stratford E20 1GR
  • Description Combined Heat and Power Plant Stratford made up of 2 generators totalling 6.6MW however the generator sizes have been inserted pro rata to achieve the overall CMU capacity of 5.838 MW as per the 3 highest export peaks
  • Company EAST LONDON ENERGY LIMITED

Technical Details

Technical Details
  • Technology Combined Heat and Power (CHP)
  • Generation Type N/A
  • Connection Type N/A
  • De-Rated Capacity 2.81
  • Connection / DSR Capacity 3.09
  • Type T-1

Auction Information

Auction Information
  • Auction 2025-26 (T-1) One Year Ahead Capacity Auction
  • Delivery Year 2,025
  • Status N/A
  • Clearing Price N/A

Additional Information

Additional Information
  • CMU ID ELES01
  • Location and Post Code 100 Montifichet Road, Westfield, Stratford E20 1GR
  • Description of CMU Components Combined Heat and Power Plant Stratford made up of 2 generators totalling 6.6MW however the generator sizes have been inserted pro rata to achieve the overall CMU capacity of 5.838 MW as per the 3 highest export peaks
  • Generating Technology Class Combined Heat and Power (CHP)
  • Company Name EAST LONDON ENERGY LIMITED
  • Auction Name 2025-26 (T-1) One Year Ahead Capacity Auction
  • _id 530,959
  • rank 0.06
  • Component ID CELESC2
  • OS Grid Reference TQ 385 847
  • Primary Fuel of Component Gas
  • Permitted on-Site Generating Unit N/A
  • Pre-Refurbishing De-Rated Capacity N/A
  • Post-Refurbishing De-Rated Capacity N/A
  • Generating Capacity of on-site Generating Unit N/A

CMU Registry Data

CMU Registry Data
  • Auction Capacity Auction
  • Type T-4
  • Delivery Year 2,028
  • Name of Applicant EAST LONDON ENERGY LIMITED
  • CM Unit Name ELE - SC

Field Value
_id 530959
Type T-1
rank 0.0573088
CMU ID ELES01
Auction Name 2025-26 (T-1) One Year Ahead Capacity Auction
Component ID CELESC2
Delivery Year 2025
De-Rated Capacity 2.81
OS Grid Reference TQ 385 847
Location and Post Code 100 Montifichet Road, Westfield, Stratford E20 1GR
Connection / DSR Capacity 3.09
Primary Fuel of Component Gas
Generating Technology Class Combined Heat and Power (CHP)
Description of CMU Components Combined Heat and Power Plant Stratford made up of 2 generators totalling 6.6MW however the generator sizes have been inserted pro rata to achieve the overall CMU capacity of 5.838 MW as per the 3 highest export peaks
Permitted on-Site Generating Unit
null
Pre-Refurbishing De-Rated Capacity
null
Post-Refurbishing De-Rated Capacity
null
Generating Capacity of on-site Generating Unit
null

Field Value
_id 15310
Type T-4
CMU ID ELES01
Auction Capacity Auction
Agent Name
null
Beta Value
null
Auction Name 2028-29 (T-4) Four Year Ahead Capacity Auction
CM Unit Name ELE - SC
CM Unit Type Non CMRS
TEC Deferral
null
Unproven DSR
null
Delivery Year 2028
Opt Out Status Opt-In
Opt-Out Reason
null
Parent Company BRING ENERGY GROUP LIMITED
DSR Test Method
null
Is FCM required
null
CM Unit Category Existing Generating CMU
Storage Facility No
De-Rated Capacity 5.62
Name of Applicant EAST LONDON ENERGY LIMITED
Primary Fuel Type Gas
Registered Holder EAST LONDON ENERGY LIMITED
Annual Penalty Cap
null
Monthly Penalty Cap
null
Proven DSR Capacity
null
DSR Bidding Capacity
null
Amount of Credit Cover
null
Termination Fee 1 Rate
null
Termination Fee 2 Rate
null
Termination Fee 3 Rate
null
Termination Fee 4 Rate
null
Termination Fee 5 Rate
null
Connection / DSR Capacity 6.179
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary
null
Pre-Refurbishing CMU Status
null
Transmission / Distribution Distribution
Unique Agreement Identifier
null
New Build Yet to Satisfy FCM
null
Planning Consents Conditions
null
Anticipated De-Rated Capacity 5.31
Term of the Capacity Agreement
null
Nature of the Security Interest
null
CMU confirmed entry into Auction Yes
Is Connection Agreement required
null
Pre-Refurbishment Bidding Status
null
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC
null
Pre-Refurbishing De-Rated Capacity
null
Date of Issue of Capacity Agreement
null
List of Traded Capacity Obligations
null
Post-Refurbishing De-Rated Capacity
null
Auction Acquired Capacity Obligation
null
Date of Issue of DSR Test Certificate
null
Has Capacity Agreement been Suspended
null
Period for which the transfer applies
null
Secondary Trading Contact - Telephone '+4407811071199
Capacity Agreement has been Terminated
null
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone
null
Delivery Years for which Agreement Valid
null
Connection Agreement Deferral Declaration
null
Date of Termination of Capacity Agreement
null
Latest Date SCM is expected to be achieved
null
Subject to Substantial Completion Milestone
null
Subject to a Minimum Completion Requirement
null
Earliest Date SCM is expected to be achieved
null
Is copy of Grid Connection Agreement required
null
Anticipated Pre-Refurbishing De-Rated Capacity
null
Anticipated Post-Refurbishing De-Rated Capacity
null
Legal Name of any Person with a Security Interest
null
Date for provision of deferred Connection Agreement
null
Duration of Capacity Agreement in First Bidding Round 1
Long-Stop Date for the Minimum Completion Requirement
null