Centrica Brigg Power Station, Scawby Brook, Brigg DN20 9LT. Map

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 95.38
  • Connection Capacity (CMU Registry) 100.60 MW
  • Anticipated Capacity (CMU Registry) 93.86 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name CBS ENERGY STORAGE ASSETS UK LIMITED
  • Parent Company (CMU Registry) Centrica plc
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4407789571247

Basic Information

Basic Information
  • Location Centrica Brigg Power Station, Scawby Brook, Brigg DN20 9LT.
  • Description Centrica Brigg Power Station is an Open Cycle Gas Turbine (OCGT) electricity generating station.
  • Company CBS ENERGY STORAGE ASSETS UK LIMITED

Technical Details

Technical Details
  • Technology OCGT and Reciprocating Engines (Fuel Type - Gas)
  • Generation Type N/A
  • Connection Type N/A
  • De-Rated Capacity N/A
  • Connection / DSR Capacity N/A
  • Type T-4

Auction Information

Auction Information
  • Auction 2021-22 (T-4) Four Year Ahead Capacity Auction
  • Delivery Year 2,021
  • Status N/A
  • Clearing Price N/A

Additional Information

Additional Information
  • CMU ID EBRGG3
  • Location and Post Code Centrica Brigg Power Station, Scawby Brook, Brigg DN20 9LT.
  • Description of CMU Components Centrica Brigg Power Station is an Open Cycle Gas Turbine (OCGT) electricity generating station.
  • Generating Technology Class OCGT and Reciprocating Engines (Fuel Type - Gas)
  • Company Name CBS ENERGY STORAGE ASSETS UK LIMITED
  • Auction Name 2021-22 (T-4) Four Year Ahead Capacity Auction
  • _id 140,125
  • rank 0.06
  • Component ID E_BRGG-1
  • OS Grid Reference SE 991 059
  • Primary Fuel of Component N/A
  • Permitted on-Site Generating Unit N/A
  • Pre-Refurbishing De-Rated Capacity N/A
  • Post-Refurbishing De-Rated Capacity N/A
  • Generating Capacity of on-site Generating Unit N/A

CMU Registry Data

CMU Registry Data
  • Auction Capacity Auction
  • Type T-4
  • Delivery Year 2,021
  • Name of Applicant CBS ENERGY STORAGE ASSETS UK LIMITED
  • CM Unit Name Brigg OCGT

Field Value
_id 140125
Type T-4
rank 0.0573088
CMU ID EBRGG3
Auction Name 2021-22 (T-4) Four Year Ahead Capacity Auction
Component ID E_BRGG-1
Delivery Year 2021
De-Rated Capacity
null
OS Grid Reference SE 991 059
Location and Post Code Centrica Brigg Power Station, Scawby Brook, Brigg DN20 9LT.
Connection / DSR Capacity
null
Primary Fuel of Component
null
Generating Technology Class OCGT and Reciprocating Engines (Fuel Type - Gas)
Description of CMU Components Centrica Brigg Power Station is an Open Cycle Gas Turbine (OCGT) electricity generating station.
Permitted on-Site Generating Unit
null
Pre-Refurbishing De-Rated Capacity
null
Post-Refurbishing De-Rated Capacity
null
Generating Capacity of on-site Generating Unit
null

Field Value
_id 5438
Type T-4
CMU ID EBRGG3
Auction Capacity Auction
Agent Name
null
Beta Value
null
Auction Name 2021-22 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Brigg OCGT
CM Unit Type CMRS
TEC Deferral
null
Unproven DSR
null
Delivery Year 2021
Opt Out Status Opt-In
Opt-Out Reason
null
Parent Company Centrica plc
DSR Test Method
null
Is FCM required
null
CM Unit Category Existing Generating CMU
Storage Facility No
De-Rated Capacity 95.375
Name of Applicant CBS ENERGY STORAGE ASSETS UK LIMITED
Primary Fuel Type Gas
Registered Holder CBS ENERGY STORAGE ASSETS UK LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity
null
DSR Bidding Capacity
null
Amount of Credit Cover (empty)
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 100.596
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary 01/10/2021 - 30/09/2022:0.000 MW
Pre-Refurbishing CMU Status
null
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2021-EBRGG3-001
New Build Yet to Satisfy FCM
null
Planning Consents Conditions
null
Anticipated De-Rated Capacity 93.862
Term of the Capacity Agreement 1
Nature of the Security Interest
null
CMU confirmed entry into Auction Yes
Is Connection Agreement required
null
Pre-Refurbishment Bidding Status
null
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC
null
Pre-Refurbishing De-Rated Capacity
null
Date of Issue of Capacity Agreement 2021-03-30
List of Traded Capacity Obligations T1: 10.368 MW; T2: 12.536 MW; T3: 5.495 MW; T4: 3.730 MW; T5: 4.565 MW; T6: -6.482 MW; T7: -1.287 MW; T8: -1.106 MW; T9: -1.869 MW; T10: -6.250 MW; T11: -2.886 MW; T12: -6.120 MW; T13: -1.152 MW; T14: -1.044 MW; T15: -1.044 MW; T16: -7.454 MW
Post-Refurbishing De-Rated Capacity
null
Auction Acquired Capacity Obligation (empty)
Date of Issue of DSR Test Certificate
null
Has Capacity Agreement been Suspended
null
Period for which the transfer applies T1: 01/10/2021 - 30/09/2022; T2: 01/10/2021 - 30/09/2022; T3: 01/10/2021 - 30/09/2022; T4: 01/10/2021 - 30/09/2022; T5: 01/10/2021 - 30/09/2022; T6: 01/10/2021 - 30/09/2022; T7: 01/10/2021 - 30/09/2022; T8: 01/10/2021 - 30/09/2022; T9: 01/10/2021 - 30/09/2022; T10: 01/10/2021 - 30/09/2022; T11: 01/10/2021 - 30/09/2022; T12: 01/10/2021 - 30/09/2022; T13: 01/10/2021 - 30/09/2022; T14: 01/10/2021 - 30/09/2022; T15: 01/10/2021 - 30/09/2022; T16: 01/10/2021 - 30/09/2022
Secondary Trading Contact - Telephone '+4407789571247
Capacity Agreement has been Terminated
null
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone
null
Delivery Years for which Agreement Valid 2021/2022
Connection Agreement Deferral Declaration
null
Date of Termination of Capacity Agreement
null
Latest Date SCM is expected to be achieved
null
Subject to Substantial Completion Milestone
null
Subject to a Minimum Completion Requirement
null
Earliest Date SCM is expected to be achieved
null
Is copy of Grid Connection Agreement required
null
Anticipated Pre-Refurbishing De-Rated Capacity
null
Anticipated Post-Refurbishing De-Rated Capacity
null
Legal Name of any Person with a Security Interest
null
Date for provision of deferred Connection Agreement
null
Duration of Capacity Agreement in First Bidding Round 1
Long-Stop Date for the Minimum Completion Requirement
null