Finlarig Power Station By Killin, Perthshire, FK21 8TX Map

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) N/A
  • Connection Capacity (CMU Registry) 16.50 MW
  • Anticipated Capacity (CMU Registry) N/A

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name SSE GENERATION LIMITED
  • Parent Company (CMU Registry) SSE plc
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +441738341632

Basic Information

Basic Information
  • Location Finlarig Power Station By Killin, Perthshire, FK21 8TX
  • Description Hydro Generating Unit
  • Company SSE GENERATION LIMITED

Technical Details

Technical Details
  • Technology Hydro
  • Generation Type N/A
  • Connection Type N/A
  • De-Rated Capacity N/A
  • Connection / DSR Capacity 16.50
  • Type T-4

Auction Information

Auction Information
  • Auction 2027-28 (T-4) Four Year Ahead Capacity Auction
  • Delivery Year 2,027
  • Status N/A
  • Clearing Price N/A

Additional Information

Additional Information
  • CMU ID FIN27R
  • Location and Post Code Finlarig Power Station By Killin, Perthshire, FK21 8TX
  • Description of CMU Components Hydro Generating Unit
  • Generating Technology Class Hydro
  • Company Name SSE GENERATION LIMITED
  • Auction Name 2027-28 (T-4) Four Year Ahead Capacity Auction
  • _id 277,376
  • rank 0.06
  • Component ID T_FINL-1
  • OS Grid Reference NN 585 345
  • Primary Fuel of Component Hydro
  • Permitted on-Site Generating Unit N/A
  • Pre-Refurbishing De-Rated Capacity 15.05
  • Post-Refurbishing De-Rated Capacity N/A
  • Generating Capacity of on-site Generating Unit N/A

CMU Registry Data

CMU Registry Data
  • Auction Capacity Auction
  • Type T-4
  • Delivery Year 2,027
  • Name of Applicant SSE GENERATION LIMITED
  • CM Unit Name Finlarig

Field Value
_id 277376
Type T-4
rank 0.0573088
CMU ID FIN27R
Auction Name 2027-28 (T-4) Four Year Ahead Capacity Auction
Component ID T_FINL-1
Delivery Year 2027
De-Rated Capacity
null
OS Grid Reference NN 585 345
Location and Post Code Finlarig Power Station By Killin, Perthshire, FK21 8TX
Connection / DSR Capacity 16.5
Primary Fuel of Component Hydro
Generating Technology Class Hydro
Description of CMU Components Hydro Generating Unit
Permitted on-Site Generating Unit
null
Pre-Refurbishing De-Rated Capacity 15.048
Post-Refurbishing De-Rated Capacity
null
Generating Capacity of on-site Generating Unit
null

Field Value
_id 14530
Type T-4
CMU ID FIN27R
Auction Capacity Auction
Agent Name
null
Beta Value
null
Auction Name 2027-28 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Finlarig
CM Unit Type CMRS
TEC Deferral
null
Unproven DSR
null
Delivery Year 2027
Opt Out Status Opt-In
Opt-Out Reason
null
Parent Company SSE plc
DSR Test Method
null
Is FCM required Yes
CM Unit Category Refurbishing Generating CMU
Storage Facility No
De-Rated Capacity
null
Name of Applicant SSE GENERATION LIMITED
Primary Fuel Type Hydro
Registered Holder SSE GENERATION LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity
null
DSR Bidding Capacity
null
Amount of Credit Cover (empty)
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 16.5
Maximum Obligation Period 15
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary
null
Pre-Refurbishing CMU Status Opt-In
Transmission / Distribution Transmission
Unique Agreement Identifier CAN-2027-FIN27R-001
New Build Yet to Satisfy FCM Yes
Planning Consents Conditions
null
Anticipated De-Rated Capacity
null
Term of the Capacity Agreement 1
Nature of the Security Interest
null
CMU confirmed entry into Auction Yes
Is Connection Agreement required
null
Pre-Refurbishment Bidding Status Pre-Refurbishing Only
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC
null
Pre-Refurbishing De-Rated Capacity 15.048
Date of Issue of Capacity Agreement 2024-04-08
List of Traded Capacity Obligations
null
Post-Refurbishing De-Rated Capacity 15.048
Auction Acquired Capacity Obligation 15.048
Date of Issue of DSR Test Certificate
null
Has Capacity Agreement been Suspended
null
Period for which the transfer applies
null
Secondary Trading Contact - Telephone '+441738341632
Capacity Agreement has been Terminated
null
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone 2025-07-11
Delivery Years for which Agreement Valid 2027/2028
Connection Agreement Deferral Declaration
null
Date of Termination of Capacity Agreement
null
Latest Date SCM is expected to be achieved 2028-05-19
Subject to Substantial Completion Milestone Yes
Subject to a Minimum Completion Requirement Yes
Earliest Date SCM is expected to be achieved 2028-04-28
Is copy of Grid Connection Agreement required
null
Anticipated Pre-Refurbishing De-Rated Capacity 15.048
Anticipated Post-Refurbishing De-Rated Capacity 15.048
Legal Name of any Person with a Security Interest
null
Date for provision of deferred Connection Agreement
null
Duration of Capacity Agreement in First Bidding Round 1
Long-Stop Date for the Minimum Completion Requirement
null