Pwlldraenllwyn, Llangwyryfon, Wales, SY23 4SR Map

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) 0.66 MW
  • De-Rated Capacity (CMU Registry) 0.66
  • Connection Capacity (CMU Registry) 9.35 MW
  • Anticipated Capacity (CMU Registry) 0.66 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name ROWAN ONSHORE WINDFARMS LIMITED
  • Parent Company (CMU Registry) EDF Energy Renewables Limited
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4402081861004

Basic Information

Basic Information
  • Location Pwlldraenllwyn, Llangwyryfon, Wales, SY23 4SR
  • Description Llangwyryfon MPAN ID: 1300050649070 The CMU is an onshore windfarm connected to the distribution system
  • Company ROWAN ONSHORE WINDFARMS LIMITED

Technical Details

Technical Details
  • Technology Onshore Wind
  • Generation Type N/A
  • Connection Type N/A
  • De-Rated Capacity 0.66
  • Connection / DSR Capacity 9.35
  • Type T-4

Auction Information

Auction Information
  • Auction 2027-28 (T-4) Four Year Ahead Capacity Auction
  • Delivery Year 2,027
  • Status N/A
  • Clearing Price N/A

Additional Information

Additional Information
  • CMU ID LNFN23
  • Location and Post Code Pwlldraenllwyn, Llangwyryfon, Wales, SY23 4SR
  • Description of CMU Components Llangwyryfon MPAN ID: 1300050649070 The CMU is an onshore windfarm connected to the distribution system
  • Generating Technology Class Onshore Wind
  • Company Name ROWAN ONSHORE WINDFARMS LIMITED
  • Auction Name 2027-28 (T-4) Four Year Ahead Capacity Auction
  • _id 1,400
  • rank 0.07
  • Component ID LNFN23
  • OS Grid Reference SN 622 694
  • Primary Fuel of Component Onshore Wind
  • Permitted on-Site Generating Unit N/A
  • Pre-Refurbishing De-Rated Capacity N/A
  • Post-Refurbishing De-Rated Capacity N/A
  • Generating Capacity of on-site Generating Unit N/A

CMU Registry Data

CMU Registry Data
  • Auction Capacity Auction
  • Type T-4
  • Delivery Year 2,027
  • Name of Applicant ROWAN ONSHORE WINDFARMS LIMITED
  • CM Unit Name Llangwyryfon

Field Value
_id 1400
Type T-4
rank 0.0706241
CMU ID LNFN23
Auction Name 2027-28 (T-4) Four Year Ahead Capacity Auction
Component ID LNFN23
Delivery Year 2027
De-Rated Capacity 0.657
OS Grid Reference SN 622 694
Location and Post Code Pwlldraenllwyn, Llangwyryfon, Wales, SY23 4SR
Connection / DSR Capacity 9.35
Primary Fuel of Component Onshore Wind
Generating Technology Class Onshore Wind
Description of CMU Components Llangwyryfon MPAN ID: 1300050649070 The CMU is an onshore windfarm connected to the distribution system
Permitted on-Site Generating Unit
null
Pre-Refurbishing De-Rated Capacity
null
Post-Refurbishing De-Rated Capacity
null
Generating Capacity of on-site Generating Unit
null

Field Value
_id 14674
Type T-4
CMU ID LNFN23
Auction Capacity Auction
Agent Name
null
Beta Value
null
Auction Name 2027-28 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Llangwyryfon
CM Unit Type Non CMRS
TEC Deferral
null
Unproven DSR
null
Delivery Year 2027
Opt Out Status Opt-In
Opt-Out Reason
null
Parent Company EDF Energy Renewables Limited
DSR Test Method
null
Is FCM required
null
CM Unit Category Existing Generating CMU
Storage Facility No
De-Rated Capacity 0.657
Name of Applicant ROWAN ONSHORE WINDFARMS LIMITED
Primary Fuel Type Onshore Wind
Registered Holder ROWAN ONSHORE WINDFARMS LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity
null
DSR Bidding Capacity
null
Amount of Credit Cover (empty)
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 9.35
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary
null
Pre-Refurbishing CMU Status
null
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2027-LNFN23-001
New Build Yet to Satisfy FCM
null
Planning Consents Conditions
null
Anticipated De-Rated Capacity 0.657
Term of the Capacity Agreement 1
Nature of the Security Interest
null
CMU confirmed entry into Auction Yes
Is Connection Agreement required
null
Pre-Refurbishment Bidding Status
null
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC
null
Pre-Refurbishing De-Rated Capacity
null
Date of Issue of Capacity Agreement 2024-04-08
List of Traded Capacity Obligations
null
Post-Refurbishing De-Rated Capacity
null
Auction Acquired Capacity Obligation 0.657
Date of Issue of DSR Test Certificate
null
Has Capacity Agreement been Suspended
null
Period for which the transfer applies
null
Secondary Trading Contact - Telephone '+4402081861004
Capacity Agreement has been Terminated
null
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone
null
Delivery Years for which Agreement Valid 2027/2028
Connection Agreement Deferral Declaration
null
Date of Termination of Capacity Agreement
null
Latest Date SCM is expected to be achieved
null
Subject to Substantial Completion Milestone
null
Subject to a Minimum Completion Requirement
null
Earliest Date SCM is expected to be achieved
null
Is copy of Grid Connection Agreement required
null
Anticipated Pre-Refurbishing De-Rated Capacity
null
Anticipated Post-Refurbishing De-Rated Capacity
null
Legal Name of any Person with a Security Interest
null
Date for provision of deferred Connection Agreement
null
Duration of Capacity Agreement in First Bidding Round 1
Long-Stop Date for the Minimum Completion Requirement
null