General Information

Key Details
  • Description A Battery Energy Storage System.
  • Auction 2028-29 (T-4) Four Year Ahead Capacity Auction
  • Delivery Year 2028
Geocoding Status: Yes

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) 39.65 MW
  • De-Rated Capacity (CMU Registry) 39.65
  • Connection Capacity (CMU Registry) 47.50 MW
  • Anticipated Capacity (CMU Registry) 39.65 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name PD688IRO LTD
  • Parent Company (CMU Registry) Pelagic Energy Development Ltd
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4407973630171

Field Value
_id 534985
Type T-4
rank 0.0573088
CMU ID SMFD28
Auction Name 2028-29 (T-4) Four Year Ahead Capacity Auction
Component ID STF28A
Delivery Year 2028
De-Rated Capacity 39.648
OS Grid Reference SU 008 874
Location and Post Code Land at Somerford Farm, SN16 9RN
Connection / DSR Capacity 47.5
Primary Fuel of Component Storage - Battery
Generating Technology Class Storage (Duration 8h)
Description of CMU Components A Battery Energy Storage System.
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 15914
Type T-4
CMU ID SMFD28
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2028-29 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Somerford
CM Unit Type CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2028
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company Pelagic Energy Development Ltd
DSR Test Method (empty)
Is FCM required Yes
CM Unit Category New Build Generating CMU
Storage Facility Yes
De-Rated Capacity 39.648
Name of Applicant PD688IRO LTD
Primary Fuel Type Storage - Battery
Registered Holder PD688IRO LTD
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover 396480
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 47.5
Maximum Obligation Period 15
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Transmission
Unique Agreement Identifier CAN-2028-SMFD28-001
New Build Yet to Satisfy FCM Yes
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 39.648
Term of the Capacity Agreement 15
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2025-04-04
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 39.648
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+4407973630171
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 15
Date for Financial Commitment Milestone 2026-07-21
Delivery Years for which Agreement Valid 2028/2029, 2029/2030, 2030/2031, 2031/2032, 2032/2033, 2033/2034, 2034/2035, 2035/2036, 2036/2037, 2037/2038, 2038/2039, 2039/2040, 2040/2041, 2041/2042, 2042/2043
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved 2028-09-30
Subject to Substantial Completion Milestone Yes
Subject to a Minimum Completion Requirement Yes
Earliest Date SCM is expected to be achieved 2025-09-01
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 15
Long-Stop Date for the Minimum Completion Requirement 2029-10-01