Home List View Map View Technologies Companies Support Us Help Login Register
Theme
Norwich East Electric Forecourt Broadland Gate Norwich NR13 5HB Map

General Information

Key Details
  • Description 6.000MW Battery Energy Storage System to be installed at Norwich East Electric Forecourt
  • Auction 2023-24 (T-1) One Year Ahead Capacity Auction
  • Delivery Year 2023
Geocoding Status: No

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) 1.12 MW
  • De-Rated Capacity (CMU Registry) 0.71
  • Connection Capacity (CMU Registry) 6 MW
  • Anticipated Capacity (CMU Registry) 0.71 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name NORWICH EAST ELECTRIC FORECOURT LTD
  • Parent Company (CMU Registry) GRIDSERVE HC LTD
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +442035402954

Field Value
_id 585906
Type T-1
rank 0.0901673
CMU ID GS_EF2
Auction Name 2023-24 (T-1) One Year Ahead Capacity Auction
Component ID GSEF02
Delivery Year 2023
De-Rated Capacity 1.116
OS Grid Reference TG 291 087
Proven DSR Capacity (empty)
Location and Post Code Norwich East Electric Forecourt Broadland Gate Norwich NR13 5HB
Connection / DSR Capacity 6
Primary Fuel of Component (empty)
Generating Technology Class Storage (Duration 1h)
Description of CMU Components 6.000MW Battery Energy Storage System to be installed at Norwich East Electric Forecourt
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 13770
Type T-4
CMU ID GS_EF2
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2026-27 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Norwich East Electric Forecourt
CM Unit Type Non CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2026
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company GRIDSERVE HC LTD
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category New Build Generating CMU
Storage Facility Yes
De-Rated Capacity 0.709
Name of Applicant NORWICH EAST ELECTRIC FORECOURT LTD
Primary Fuel Type Storage - Battery
Registered Holder NORWICH EAST ELECTRIC FORECOURT LTD
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate £5000.00 /MW
Termination Fee 2 Rate £25000.00 /MW
Termination Fee 3 Rate £10000.00 /MW
Termination Fee 4 Rate £15000.00 /MW
Termination Fee 5 Rate £35000.00 /MW
Connection / DSR Capacity 6
Maximum Obligation Period 3
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2026-GS_EF2-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 0.709
Term of the Capacity Agreement 3
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2023-03-31
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 0.688
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone '+442035402954
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 3
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2026/2027, 2027/2028, 2028/2029
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved 2023-01-09
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved 2022-12-07
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 3
Long-Stop Date for the Minimum Completion Requirement (empty)