Ratcliffe-on-Soar Nottingham NG11 0EE Map

General Information

Key Details
  • Description Ratcliffe Unit 3 coal-fired unit
  • Auction 2023-24 (T-4) Four Year Ahead Capacity Auction
  • Delivery Year 2023
Geocoding Status: Yes

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 0
  • Connection Capacity (CMU Registry) 515 MW
  • Anticipated Capacity (CMU Registry) 0 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name Uniper Global Commodities SE
  • Parent Company (CMU Registry) N/A
  • Secondary Trading Email (CMU Registry) N/A
  • Secondary Trading Phone (CMU Registry) N/A

Field Value
_id 332117
Type T-4
rank 0.0901673
CMU ID RATS33
Auction Name 2023-24 (T-4) Four Year Ahead Capacity Auction
Component ID T_RATS-3
Delivery Year 2023
De-Rated Capacity (empty)
OS Grid Reference SK 503 301
Location and Post Code Ratcliffe-on-Soar Nottingham NG11 0EE
Connection / DSR Capacity (empty)
Primary Fuel of Component (empty)
Generating Technology Class Coal
Description of CMU Components Ratcliffe Unit 3 coal-fired unit
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 2095
Type T-4
CMU ID RATS-3
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2018-19 (T-4) Four Year Ahead Capacity Auction
CM Unit Name RATS3
CM Unit Type CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2018
Opt Out Status Opt-In
Opt-Out Reason N/A (Opt-in)
Parent Company (empty)
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category Refurbishing CMU
Storage Facility (empty)
De-Rated Capacity (empty)
Name of Applicant Uniper Global Commodities SE
Primary Fuel Type (empty)
Registered Holder Uniper Global Commodities SE
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate £5,000/MW
Termination Fee 2 Rate £25,000/MW
Termination Fee 3 Rate (empty)
Termination Fee 4 Rate (empty)
Termination Fee 5 Rate (empty)
Connection / DSR Capacity 515
Maximum Obligation Period 3
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary (empty)
Pre-Refurbishing CMU Status Refurbishing and Existing CM Unit
Transmission / Distribution Transmission
Unique Agreement Identifier CAN-2018-RATS-3-00001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity (empty)
Term of the Capacity Agreement 1
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required
Pre-Refurbishment Bidding Status Refurbishing and Existing CM Unit
Secondary Trading Contact - Email (empty)
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity 440.713
Date of Issue of Capacity Agreement 2015-01-30
List of Traded Capacity Obligations (empty)
Post-Refurbishing De-Rated Capacity 451.346
Auction Acquired Capacity Obligation 451.346
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies (empty)
Secondary Trading Contact - Telephone (empty)
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2018/2019
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required
Anticipated Pre-Refurbishing De-Rated Capacity 439.9528
Anticipated Post-Refurbishing De-Rated Capacity 451.346
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 3
Long-Stop Date for the Minimum Completion Requirement (empty)