land adjacent to the AYRSHIRE GRID 400KV COLLECTOR SUBSTATION, Cambelton Farm, Beech Avenue, Hunterston, West Kilbride, KA23 9QF.
4 Components Storage (Duration 4h) FLEXIBLEGRIDPOWER2 LTD
Total Capacity: 73.38 MW
Components: 4
Technologies:
Storage (Duration 4h)
Unique CMUs: 4

Secondary Trading Contacts

Contact Information

Component Descriptions

Lithium ion battery storage plant

Used by 4 CMUs

Components at this Location

Lithium ion battery storage plant
CMU: H12245
Storage (Duration 4h) FLEXIBLEGRIDPOWER2 LTD Parent: Hunterston Grid Complex Limited
Capacity Information:
De-Rated Capacity (Registry) 18.344
Connection/DSR Capacity 40
Anticipated Capacity 18.344
CMU: H12246
Storage (Duration 4h) FLEXIBLEGRIDPOWER2 LTD Parent: Hunterston Grid Complex Limited
Capacity Information:
De-Rated Capacity (Registry) 18.344
Connection/DSR Capacity 40
Anticipated Capacity 18.344
CMU: H22245
Storage (Duration 4h) FLEXIBLEGRIDPOWER2 LTD Parent: Hunterston Grid Complex Limited
Capacity Information:
De-Rated Capacity (Registry) 18.344
Connection/DSR Capacity 40
Anticipated Capacity 18.344
CMU: H22246
Storage (Duration 4h) FLEXIBLEGRIDPOWER2 LTD Parent: Hunterston Grid Complex Limited
Capacity Information:
De-Rated Capacity (Registry) 18.344
Connection/DSR Capacity 40
Anticipated Capacity 18.344