Home Technologies Companies Locations Map Explorer FAQ Trading Board Buy Me A Coffee Help Login Register
Theme
Light Dark Auto

Cadeby 1 CMM Generation Garden Lane Cadeby Doncaster DN5 7SN - Gas fired generating sets.

Component ID: A41708
Last updated: 29 Jul 2025 23:06 UTC
CMU ID:
Description:
Gas fired generating sets.
Auction:
2021-22 (T-4) Four Year Ahead Capacity Auction

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 11.32
  • Connection Capacity (CMU Registry) 11.94 MW
  • Anticipated Capacity (CMU Registry) 11.32 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name REGENT PARK ENERGY LIMITED
  • Parent Company (CMU Registry) Alkane Energy Limited
  • Secondary Trading Email (CMU Registry) [email protected]
  • Secondary Trading Phone (CMU Registry) +4401604662400

Field Value
_id 114129
Type T-4
rank 0.0573088
CMU ID A41708
Auction Name 2021-22 (T-4) Four Year Ahead Capacity Auction
Component ID Cadeb1
Delivery Year 2021
De-Rated Capacity (empty)
OS Grid Reference SE 517 004
Location and Post Code Cadeby 1 CMM Generation Garden Lane Cadeby Doncaster DN5 7SN
Connection / DSR Capacity (empty)
Primary Fuel of Component (empty)
Generating Technology Class OCGT and Reciprocating Engines
Description of CMU Components Gas fired generating sets.
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 5128
Type T-4
CMU ID A41708
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2021-22 (T-4) Four Year Ahead Capacity Auction
CM Unit Name A41708
CM Unit Type Non CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2021
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company Alkane Energy Limited
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category Existing Generating CMU
Storage Facility No
De-Rated Capacity 11.324
Name of Applicant REGENT PARK ENERGY LIMITED
Primary Fuel Type Gas
Registered Holder REGENT PARK ENERGY LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate Β£5000.00 /MW
Termination Fee 2 Rate Β£25000.00 /MW
Termination Fee 3 Rate Β£10000.00 /MW
Termination Fee 4 Rate Β£15000.00 /MW
Termination Fee 5 Rate Β£35000.00 /MW
Connection / DSR Capacity 11.944
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary 01/10/2021 - 30/09/2022:4.324 MW
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2021-A41708-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 11.324
Term of the Capacity Agreement 1
Nature of the Security Interest (empty)
CMU confirmed entry into Auction Yes
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email [email protected]
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2018-03-20
List of Traded Capacity Obligations T1: -5.000 MW; T2: -2.000 MW
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation 11.324
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies T1: 01/10/2021 - 30/09/2022; T2: 01/10/2021 - 30/09/2022
Secondary Trading Contact - Telephone '+4401604662400
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2021/2022
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round 1
Long-Stop Date for the Minimum Completion Requirement (empty)