Engie Great Coates, Grimsby, DN31 2TT - Combined Heat and Power Plant Grimsby made up of 5 generators totalling 30MW however the export capacity is limited to 6.MW (other generators are on site are defunct) so the participating generator sizes have been inserted pro rata to achieve the overall CMU capacity of 5.943 MW as per the 3 highest export peaks.

Component ID: CES0C3
Last updated: 28 Jul 2025 17:02 UTC
CMU ID:
Technology:
N/A
Description:
Combined Heat and Power Plant Grimsby made up of 5 generators totalling 30MW however the export capacity is limited to 6.MW (other generators are on site are defunct) so the participating generator sizes have been inserted pro rata to achieve the overall CMU capacity of 5.943 MW as per the 3 highest export peaks.
Auction:
2020-21 (T-4) Four Year Ahead Capacity Auction

Technical Capacity Information

Capacity Metrics
  • De-Rated Capacity (Component DB) N/A
  • De-Rated Capacity (CMU Registry) 5.38
  • Connection Capacity (CMU Registry) 5.98 MW
  • Anticipated Capacity (CMU Registry) 5.38 MW

Note: De-rated capacity typically accounts for availability factors. Connection capacity represents the maximum grid connection size. Values sourced from Component database or CMU Registry as indicated.

Contact & Ownership

Company Information
  • Applicant / Company Name INDUSTRIAL ENERGY SERVICES LIMITED
  • Parent Company (CMU Registry) N/A
  • Secondary Trading Email (CMU Registry) N/A
  • Secondary Trading Phone (CMU Registry) +4402082216530

Field Value
_id 220615
Type ST
rank 0.0573088
CMU ID CES0C3
Auction Name 2020-21 (T-4) Four Year Ahead Capacity Auction
Component ID HUMGT1
Delivery Year 2020
De-Rated Capacity (empty)
OS Grid Reference TA 237 124
Location and Post Code Engie Great Coates, Grimsby, DN31 2TT
Connection / DSR Capacity (empty)
Primary Fuel of Component (empty)
Generating Technology Class (empty)
Description of CMU Components Combined Heat and Power Plant Grimsby made up of 5 generators totalling 30MW however the export capacity is limited to 6.MW (other generators are on site are defunct) so the participating generator sizes have been inserted pro rata to achieve the overall CMU capacity of 5.943 MW as per the 3 highest export peaks.
Permitted on-Site Generating Unit (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Post-Refurbishing De-Rated Capacity (empty)
Generating Capacity of on-site Generating Unit (empty)

Field Value
_id 3830
Type ST
CMU ID CES0C3
Auction Capacity Auction
Agent Name (empty)
Beta Value (empty)
Auction Name 2020-21 (T-4) Four Year Ahead Capacity Auction
CM Unit Name Humber
CM Unit Type Non CMRS
TEC Deferral (empty)
Unproven DSR (empty)
Delivery Year 2020
Opt Out Status Opt-In
Opt-Out Reason (empty)
Parent Company (empty)
DSR Test Method (empty)
Is FCM required (empty)
CM Unit Category Existing Generating CMU
Storage Facility No
De-Rated Capacity 5.38
Name of Applicant INDUSTRIAL ENERGY SERVICES LIMITED
Primary Fuel Type (empty)
Registered Holder INDUSTRIAL ENERGY SERVICES LIMITED
Annual Penalty Cap 1
Monthly Penalty Cap 2
Proven DSR Capacity (empty)
DSR Bidding Capacity (empty)
Amount of Credit Cover (empty)
Termination Fee 1 Rate Β£5000.00 /MW
Termination Fee 2 Rate Β£25000.00 /MW
Termination Fee 3 Rate Β£10000.00 /MW
Termination Fee 4 Rate Β£15000.00 /MW
Termination Fee 5 Rate Β£35000.00 /MW
Connection / DSR Capacity 5.98
Maximum Obligation Period 1
Capacity Agreement Awarded Yes
Pre-Qualification Decision Prequalified
Capacity obligation Summary 01/10/2020 - 22/11/2020:0.000 MW; 23/11/2020 - 30/09/2021:5.380 MW
Pre-Refurbishing CMU Status (empty)
Transmission / Distribution Distribution
Unique Agreement Identifier CAN-2020-CES0C3-001
New Build Yet to Satisfy FCM (empty)
Planning Consents Conditions (empty)
Anticipated De-Rated Capacity 5.382
Term of the Capacity Agreement 1
Nature of the Security Interest (empty)
CMU confirmed entry into Auction (empty)
Is Connection Agreement required (empty)
Pre-Refurbishment Bidding Status (empty)
Secondary Trading Contact - Email (empty)
Date for provision of deferred TEC (empty)
Pre-Refurbishing De-Rated Capacity (empty)
Date of Issue of Capacity Agreement 2020-11-20
List of Traded Capacity Obligations T1: 5.380 MW
Post-Refurbishing De-Rated Capacity (empty)
Auction Acquired Capacity Obligation (empty)
Date of Issue of DSR Test Certificate (empty)
Has Capacity Agreement been Suspended (empty)
Period for which the transfer applies T1: 23/11/2020 - 30/09/2021
Secondary Trading Contact - Telephone '+4402082216530
Capacity Agreement has been Terminated (empty)
Duration of Capacity Agreement Awarded 1
Date for Financial Commitment Milestone (empty)
Delivery Years for which Agreement Valid 2020/2021
Connection Agreement Deferral Declaration (empty)
Date of Termination of Capacity Agreement (empty)
Latest Date SCM is expected to be achieved (empty)
Subject to Substantial Completion Milestone (empty)
Subject to a Minimum Completion Requirement (empty)
Earliest Date SCM is expected to be achieved (empty)
Is copy of Grid Connection Agreement required (empty)
Anticipated Pre-Refurbishing De-Rated Capacity (empty)
Anticipated Post-Refurbishing De-Rated Capacity (empty)
Legal Name of any Person with a Security Interest (empty)
Date for provision of deferred Connection Agreement (empty)
Duration of Capacity Agreement in First Bidding Round (empty)
Long-Stop Date for the Minimum Completion Requirement (empty)