Woodhouse Energy Centre A. Pearson and Sons? Nursery Alderley Edge SK9 7UW (13 components)
• The CMU Component will have a connection capacity of 3.376MW. Gas-fired reciprocating engine will be the technology used.
• The CMU component is installed in the Woodhouse Energy Centre that is located at a Nursery site in Alderley Edge.
• The CMU component, CASQ17 supplies heat, CO2 and electricity to the onsite nursery and facilities.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
3.08 MW
41.84 MW
Winnington CHP Winnington Lane Winnington Northwich Cheshire CW8 4GX (37 components)
• Continuously operating, maximum output GE gas turbine driving a 47.020MVA Alstom generator at 0.85 power factor. (2)
• Continuously operating, maximum output GE gas turbine driving a 47.020MWA Alstom generator at 0.85 power factor.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
2921.10 MW
Wight Salads Arreton Newport Isle of Wight PO30 3AR (6 components)

The CMU component will have a connection capacity of 6MW. Gas-fired reciprocating engine will be the technology used

Active • 2024-25 (T-4), 2023-24 (T-4) ...
Westland Nurseries (Offenham) Ltd., Station Road, Offenham, Evesham, Worcestershire, WR11 8LW (14 components)
• Gas CHP in a horticultiral environment providing heat for crop growth
• One asset 1.5MW CHP engine in a horticultural environment with no auxiliary load.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
0.91 MW
Westexe, Tiverton, Devon, EX16 5LL (8 components)

2026 kW CHP unit

Active • 2026-27 (T-4), 2025-26 (T-4) ...
1.83 MW
WEMBLEY ENERGY CENTRE, HARBUTT ROAD, OFF ENGINEERS WAY, WEMBLEY, LONDON, HA9 0NH (6 components)

A gas engine CHP site providing hot water to a local district heating network

Active • 2028-29 (T-4), 2027-28 (T-4) ...
University of Warwick, Coventry, CV4 7AL (59 components)
• One of six CHP units at University of Warwick, Coventry, CV4 7AL
• One of six CHP units at University of Warwick, Coventry, CV4 7AL.
Active • 2024-25 (T-4), 2023-24 (T-4) ...
0.90 MW
0.91 MW
Treviscoe Dryer, Little Treviscoe, St. Austell, PL26 7QN (11 components)
• Gas CHP in St. Austell
• Gas fired CHP unit
Active • 2026-27 (T-4), 2025-26 (T-4) ...
3.06 MW
Tower Nurseries Netherhall Road Roydon Essex CM19 5JP (12 components)
• Gas CHP engines 1.5MW and 1.48MW. Primary fuel type = Natural Gas
• Gas engines in commercial horticultural environment with no auxilliary load. All generation unit capacities are nominal and allow for site-specific variations
Active • 2028-29 (T-4), 2026-27 (T-4) ...
2.72 MW
TOTAL LINDSEY OIL REFINERY LTD, EASTFIELD ROAD, NORTH KILLINGHOLME, IMMINGHAM, DN40 3LW (6 components)
• On-Site Generating CMU.
• On-Site Generating Steam Turbine, utilising heat recovery waste as a 'fuel input' and generating electricity w/o fossil fuel emissions.
• On-Site Generating Steam Turbine, utilising high pressure steam waste from on-site refinery processes as a 'fuel input' and generating electricity w/o fossil fuel emissions.
Active • 2025-26 (T-1), 2024-25 (T-4) ...
38.03 MW
The Ridgeway Enfield, Middlesex EN2 8JL (10 components)

On-site CHP - existing generating unit The Ridgeway Enfield, Middlesex EN2 8JL OS Grid Reference: TQ 312 980

Active • 2027-28 (T-4), 2026-27 (T-4) ...
1.02 MW
The Old Airfield, City Fields Way, Tangmere, Chichester West Sussex PO20 2FT (15 components)

Four CHP engines in a horticultural environment with no auxilliary load. All generation unit capacities are nominal and allow for site-specific variations. (3)

Active • 2028-29 (T-4), 2025-26 (T-4) ...
6.37 MW
The Heat Station Harbour Parade, Southampton, Hampshire, SO15 1BA (31 components)
• 1.0MW Combined heat and Power Plant Plant at the Heat Station is made up of 2 generators totalling 6.7MW however the generator sizes have been inserted pro rata to achieve the overall CMU capacity of 5.430MW as per the 3 highest export peaks
• 5.7MW Combined heat and Power Plant Plant at the Heat Station is made up of 2 generators totalling 6.7MW however the generator sizes have been inserted pro rata to achieve the overall CMU capacity of 6.038MW as per the 3 highest export peaks
• 5.7MW Combined heat and Power Plant Plant at the Heat Station is made up of 2 generators totalling 6.7MW however the generator sizes have been inserted pro rata to achieve the overall CMU capacity of 5.430MW as per the 3 highest export peaks.
Active • 2025-26 (T-4), 2025-26 (T-1) ...
4.94 MW
Thearne Lane, Woodmansey, Beverley, North Humberside, HU17 0SA (3 components)

2 x CHP at a horticultural site

Active • 2028-29 (T-4), 2025-26 (T-4) ...
2.33 MW
Thearne Lane Woodmansey Beverley HU17 0SA (7 components)
• Gas CHP engines in commercial horticultural environment with no auxilliary load
• Two gas CHP engines in commercial horticultural environment with no auxilliary load
Active • 2027-28 (T-4), 2025-26 (T-4) ...
1.05 MW
Thanet Earth Plot 2, 2 Barrow Man Road Birchington Kent CT7 0AX (10 components)
• CHP engine in horticultural environment with no auxilliary load
• Two CHP engines in horticultural environment with no auxilliary load
Active • 2028-29 (T-4), 2025-26 (T-4) ...
5.82 MW
Tees Valley Nursery, The Moat, Belasis Hall, TS23 4ED (26 components)
• The CMU component TEES01 is one gas-fired Jenbacher CHP engine. It will be supplying heat, CO2 and power to the on-site tomato Nursery all year.
• The CMU component TEES02 is one gas-fired Jenbacher CHP engine. It will be supplying heat, CO2 and power to the on-site tomato Nursery all year.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
6.17 MW
Stubbins Hall Lane Waltham Abbey Essex EN9 2EE (7 components)
• Gas engines 1.54MW and 1.54MW in commercial horticultural environment with no auxilliary load. Only one engine used for Capacity Market purposes
• Two gas CHP engines 1.54MW. Primary fuel type = Natural Gas
Active • 2028-29 (T-4), 2025-26 (T-1) ...
1.45 MW
St Marks Boilerhouse Donaldson Road LEICESTER Leicestershire LE4 6BF (17 components)

Combined Heat and Power Plant, St Marks Boiler House, capacity of generator 1.600MW. Although the supplier of the settled hh meter has provided their three peaks, we have used the … (3)

Active • 2028-29 (T-4), 2027-28 (T-4) ...
30.21 MW
Staverton, Trowbridge, Wiltshire, BA14 6PH (22 components)

Turbomach M50 Natural Gas fired CHP unit

Active • 2024-25 (T-4), 2023-24 (T-1) ...
7.60 MW