Thearne Lane Woodmansey Beverley HU17 0SA (7 components)
• Gas CHP engines in commercial horticultural environment with no auxilliary load
• Two gas CHP engines in commercial horticultural environment with no auxilliary load
Active • 2027-28 (T-4), 2025-26 (T-4) ...
1.05 MW
Thanet Earth Plot 2, 2 Barrow Man Road Birchington Kent CT7 0AX (10 components)
• CHP engine in horticultural environment with no auxilliary load
• Two CHP engines in horticultural environment with no auxilliary load
Active • 2028-29 (T-4), 2025-26 (T-4) ...
5.82 MW
1.27 MW
Tees Valley Nursery, The Moat, Belasis Hall, TS23 4ED (26 components)
• The CMU component TEES01 is one gas-fired Jenbacher CHP engine. It will be supplying heat, CO2 and power to the on-site tomato Nursery all year.
• The CMU component TEES02 is one gas-fired Jenbacher CHP engine. It will be supplying heat, CO2 and power to the on-site tomato Nursery all year.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
6.17 MW
Stoneykirk Road, Stranraer, DG9 7BU (16 components)
• CHP unit
• Gas fired CHP unit
Active • 2024-25 (T-1), 2023-24 (T-1) ...
3.58 MW
St Marks Boilerhouse Donaldson Road LEICESTER Leicestershire LE4 6BF (17 components)

Combined Heat and Power Plant, St Marks Boiler House, capacity of generator 1.600MW. Although the supplier of the settled hh meter has provided their three peaks, we have used the … (3)

Active • 2028-29 (T-4), 2027-28 (T-4) ...
30.21 MW
Staverton, Trowbridge, Wiltshire, BA14 6PH (22 components)

Turbomach M50 Natural Gas fired CHP unit

Active • 2024-25 (T-4), 2023-24 (T-1) ...
7.60 MW
Station Road, Wigton, Cumbria CA7 9BG (37 components)
• Back pressure steam turbine
• Gas engine
• Gas turbine
Active • 2024-25 (T-4), 2024-25 (T-1) ...
22.35 MW
Staithes Road, Preston, Hull, HU12 8TB (23 components)

Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms. (3)

Active • 2028-29 (T-4), 2027-28 (T-4) ...
24.24 MW
Stainland Boardmill, Holywell Green, Halifax, HX4 9PY (4 components)

Gas Fired CHP

Active • 2027-28 (T-4), 2026-27 (T-4) ...
Speke Blvd, Speke, Liverpool L24 9LE (4 components)
• On-site Generating CMU
• on site generating CMU
Active • 2025-26 (T-1), 2024-25 (T-1) ...
3.20 MW
SOUTH STAFFORDSHIRE WATER PLC, Hampton Loade Treatment Works, Hampton Loade, Bridgnorth, WV15 6HD (13 components)

Existing Generation on existing site - CHP

Active • 2027-28 (T-4), 2026-27 (T-4) ...
4.94 MW
Southport & Formby District General Hospital, Town Lane Kew, Southport PR8 6PN (2 components)

1 x gas reciprocating engine with a total rated gross power capacity of 0.995 MW and a net power capacity of 0.961 MW (2)

Active • 2028-29 (T-4), 2025-26 (T-1)
1.73 MW
Southampton General Hospital Tremona Road, Southampton, SO16 6YD (10 components)
• 2*2 gas reciprocating engines with a total gross power capacity of 3.973 MW and a net power capacity of 3.953 MW.
• 2*2 gas reciprocating engines with a total gross power capacity of 4.00 MW and a net power capacity of 3.960 MW.
• 2X gas reciprocating engines with a total gross power capacity of 3.973 MW
Active • 2028-29 (T-4), 2027-28 (T-4) ...
3.59 MW
Solvay, Trinity St, Oldbury, B69 4LW (8 components)

Existing Generation on existing site - CHP

Active • 2027-28 (T-4), 2026-27 (T-4) ...
1.17 MW
Solenis, Cleckheaton Road, Low Moor, Bradford, United Kingdom, BD12 0JZ (11 components)
• Gas Turbine CHP unit
• Steam turbine
Active • 2024-25 (T-1), 2023-24 (T-4) ...
Snodland Paper Mill, Mill Street, Snodland, Kent, ME6 5AX (4 components)

On-site Generating CMU. (3)

Active • 2028-29 (T-4), 2025-26 (T-1) ...
37.93 MW
Smurfit Kappa SSK, Mount Street, Nechells, Birmingham B7 5RE (14 components)
• 8.300MW Gas Turbine installation
• 8.3MW Gas Turbine installation
Active • 2027-28 (T-4), 2026-27 (T-4) ...
7.58 MW
Slough Nurseries, Rochford Gardens, Uxbridge Road, Slough SL2 5NU (4 components)

One 2MW gas CHP engine in a horticultural environment

Active • 2027-28 (T-4), 2024-25 (T-1) ...
1.78 MW
Shottentons Farm, Pecks Hill, Nazeing, Essex, EN9 2NY (11 components)

Gas fuelled CHP generation plant

Active • 2027-28 (T-4), 2025-26 (T-4) ...
4.58 MW
Sembcorp UK Headquarters Wilton International Middlesbrough TS90 8WS United Kingdom (14 components)
• CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). S20G02 is a OCGT in CHP Configuration within the (former ICI) Wilton Site.
• CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). S21G02 is a OCGT in CHP Configuration within the (former ICI) Wilton Site.
• CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). S26G02 is a OCGT in CHP Configuration within the (former ICI) Wilton Site.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
38.65 MW
Sembcorp UK Headquarters, Wilton International, Middlesbrough, TS90 8WS (23 components)
• (Please note: CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). S23S11 is a Steam Turbine in CHP Configuration within the (former ICI) Wilton Site.
• (Please note: CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1). Unit is a OCGT and Steam Turbine in CHP Configuration within the (former ICI) Wilton Site.
• S23G03 will be a OCGT in CHP Configuration within the (former ICI) Wilton Site. CMU Metering is embedded behind Grid Connection Site: Wilton 66kV Substation. BM Unit T_WILCT-1.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
58.48 MW
School Road, Aberdeen AB24 1TU (18 components)
• District heating implementation with one asset 1.943MW exporting excess to distribution network. Primary fuel type = Natural Gas
• District heating implementation with one asset 1.943MW exporting excess to distribution network. Primary fuel type = Natural Gas. All generation unit capacities are nominal and allow for site-specific variations.
Active • 2028-29 (T-4), 2027-28 (T-4) ...
1.73 MW