Reciprocating engines

12 unique locations (425 components)

EDF Energy, Torness power station, Torness, Dunbar, East Lothian, EH42 1QU (34 components)
• Torness Power Station CMU 1: [TN1-23] T_TORN-1 + (50% x T_TORN-D)
• Torness Power Station CMU 1: [TN1-24] T_TORN-1 + (50% x T_TORN-D)
• Torness Power Station CMU 2: [TN2-24] T_TORN-2 + (50% x T_TORN-D)
Active • 2028-29 (T-4), 2027-28 (T-4) ...
3068.68 MW
EDF Energy, Torness power station, Torness, Dunbar, East Lothian, EH42 1QS (14 components)
• 1.9 MW Gas gen ENER-G 1999
• Torness Power Station CMU 1: [TN1-17] T_TORN-1 + (50% x T_TORN-D)
• Torness Power Station CMU 2: [TN2-17] T_TORN-2 + (50% x T_TORN-D)
Active • 2024-25 (T-4), 2021-22 (T-4) ...
1099.77 MW
EDF Energy (Thermal Generation) Limited, Cottam Power Station, Outgang Lane, Cottam, Retford, DN22 0NP (46 components)
• 2MW - 2.3MWh Battery Energy Storage System
• CMU INO200 represents demand assets on the Inovyn ChlorVinyls Ltd site in Runcorn, Cheshire. The asset uses electricity for Chemical manufacture. Site load can easily be altered to suit demand or reduction.
• Load Response ? Automated. Dispatch via Proprietary Panel encompassing industrial computer, smart meters, smart I/O &/or serial comms. Placeholder component for empty Unproven DSR CMU - Load Reduction upon instruction
Active • 2027-28 (T-4), 2025-26 (T-4) ...
1528.52 MW
EDF Energy, Sizewell B power station, Nr Leiston, Suffolk, IP16 4UR (39 components)
• Sizewell B Power Station CMU 1: [SZ1-24] T_SIZB-1 + (50% x T_SIZB-D)
• Sizewell B Power Station CMU 2: [SZ2-23] T_SIZB-2 + (50% x T_SIZB-D)
• Sizewell B Power Station CMU 2: [SZ2-24] T_SIZB-2 + (50% x T_SIZB-D)
Active • 2028-29 (T-4), 2027-28 (T-4) ...
4640.16 MW
EDF Energy, Hunterston B power station, West Kilbride, Ayrshire, KA23 9QX (40 components)
• Existing CCGT Unit
• Hunterston B Power Station CMU 7: [HU7-21] T_HUNB-7 + (50% x T_HUNB-D) + (50% x E_HUNB-11S)
• Hunterston B Power Station CMU 8: [HU8-21] T_HUNB-8 + (50% x T_HUNB-D) + (50% x E_HUNB-11S)
Active • 2025-26 (T-4), 2024-25 (T-4) ...
1607.21 MW
EDF Energy, Hinkley Point B power station, Nr Bridgwater, Somerset, TA5 1UD (56 components)
• Hinkley Point B Power Station CMU 7: [HP7-22] T_HINB-7 + (50% x T_HINB-D)
• Hinkley Point B Power Station CMU 7: [HP7-23] T_HINB-7 + (50% x T_HINB-D)
• Hinkley Point B Power Station CMU 8: [HP8-23] T_HINB-8 + (50% x T_HINB-D)
Active • 2027-28 (T-4), 2026-27 (T-4) ...
1771.09 MW
EDF Energy, Heysham 2 power station, Morecambe, Lancashire, LA3 2XH (43 components)
• Heysham 2 Power Station CMU 7: [HY2723] T_HEYM27 + (50% x T_HEYM2-D)
• Heysham 2 Power Station CMU 7: [HY2724] T_HEYM27 + (50% x T_HEYM2-D)
• Heysham 2 Power Station CMU 8: [HY2824] T_HEYM28 + (50% x T_HEYM2-D)
Active • 2028-29 (T-4), 2027-28 (T-4) ...
3985.39 MW
EDF Energy, Heysham 1 power station, Morecambe, Lancashire, LA3 2XH (33 components)
• EV charge station
• Heysham 1 Power Station CMU 1: [HY1124] T_HEYM11
• Heysham 1 Power Station CMU 2: [HY1224] T_HEYM12
Active • 2028-29 (T-4), 2026-27 (T-4) ...
2591.79 MW
EDF Energy, Hartlepool power station, Tees Road, Hartlepool, TS25 2BZ (57 components)
• Hartlepool Power Station CMU 2: [HR2-23] T_HRTL-2
• Hartlepool Power Station CMU 2: [HR2-24] T_HRTL-2
• Hartlepool Power Station CMU 1: [HR1-24] T_HRTL-1
Active • 2028-29 (T-4), 2027-28 (T-4) ...
5859.76 MW
EDF Energy, Dungeness B power station, Romney Marsh, Kent, TN29 9PX (41 components)
• Dungeness B Power Station CMU 21: [DN2124] T_DNGB21 + (50% x T_DNGB-D)
• Dungeness B Power Station CMU 22: [DN2223] T_DNGB22 + (50% x T_DNGB-D)
• Dungeness B Power Station CMU 22: [DN2224] T_DNGB22 + (50% x T_DNGB-D)
Active • 2028-29 (T-4), 2027-28 (T-4) ...
1489.08 MW
Cantelo Reception, UK Power Reserve Ltd, Bradon Farm, Isle Abbots, Taunton, Somerset. TA3 6RX (17 components)
• New build battery storage.
• The CMU is a electro-chemical Lithium-ion battery storage system connected to the transmission system at the National Grid Transmission Substation.
• The CMU will be formed of multiple individual gas generating units controlled centrally and exporting to the distribution system.
Active • 2027-28 (T-4), 2026-27 (T-4) ...
31.11 MW
BSB Transport Ltd Trondheim Way, Redwood Park Estate, Stallingborough, Grimsby, North East Lincolnshire, DN41 8FD. (5 components)
• 1.9 MW Gas gen ENER-G 1999
• A Battery Energy Storage System.
• Hunterston B Power Station CMU 7: [HU7-19] T_HUNB-7 + (50% x T_HUNB-D) + (50% x E_HUNB-11S)
Active • 2025-26 (T-1), 2024-25 (T-1) ...
61.58 MW
Loading map...
Showing 12 locations